Overview
SHRI RAM PARK
SHRI RAM BUILDER AND DEVELOPERS · BILASPUR
Units50
Booked24 of 50As of 2026-06-30
Construction progress63%As of 2026-06-30
Completion2029-12-10Revised · Proposed 2029-08-10
Registered on2024-08-30
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 8 quarters |
| Technical report | |
| Site & area | 3 site details · 50 unit types |
| Construction & progress | 4 progress details · 8 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 56 documents · 6 source links |
Registration
Registration
| Promoter | SHRI RAM BUILDER AND DEVELOPERS | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA300824001817 | |
| Registered on | 2024-08-30 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2029-08-10 | |
| Revised completion | 2029-12-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,66,26,000 | |
|---|---|---|
| Construction | ₹2,92,93,000 |
Quarterly money flows
| 2024-Q3 | ₹0 |
| 2024-Q4 | ₹0 |
| 2025-Q1 | ₹0 |
| 2025-Q2 | ₹0 |
| 2025-Q3 | ₹0 |
| 2025-Q4 | ₹5,89,645 |
| 2026-Q1 | ₹11,48,046 |
| 2026-Q2 | ₹6,26,099 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 50 | |
|---|---|---|
| Booked | 24 | |
| Booked as of | 2026-06-30 |
Unit types
| PLOT-1 | 1 | 1 |
| PLOT-2 | 1 | 1 |
| PLOT-3 | 1 | 0 |
| PLOT-4 | 1 | 1 |
| PLOT-5 | 1 | 0 |
| PLOT-6 | 1 | 1 |
| PLOT-7 | 1 | 0 |
| PLOT-8 | 1 | 0 |
| PLOT-9 | 1 | 0 |
| PLOT-10 | 1 | 0 |
| PLOT-11 | 1 | 0 |
| PLOT-12 | 1 | 0 |
| PLOT-13 | 1 | 0 |
| PLOT-14 | 1 | 0 |
| PLOT-15 | 1 | 1 |
| PLOT-16 | 1 | 0 |
| PLOT-17 | 1 | 0 |
| PLOT-18 | 1 | 0 |
| PLOT-19 | 1 | 1 |
| PLOT-20 | 1 | 1 |
| PLOT-21 | 1 | 1 |
| PLOT-22 | 1 | 1 |
| PLOT-23 | 1 | 1 |
| PLOT-24 | 1 | 1 |
| PLOT-25 | 1 | 1 |
| PLOT-26 | 1 | 0 |
| PLOT-27 | 1 | 0 |
| PLOT-28 | 1 | 0 |
| PLOT-29 | 1 | 0 |
| PLOT-30 | 1 | 0 |
| PLOT-31 | 1 | 0 |
| PLOT-32 | 1 | 1 |
| PLOT-33 | 1 | 1 |
| PLOT-34 | 1 | 1 |
| PLOT-35 | 1 | 1 |
| PLOT-36 | 1 | 1 |
| PLOT-37 | 1 | 1 |
| PLOT-38 | 1 | 1 |
| PLOT-39 | 1 | 0 |
| PLOT-40 | 1 | 0 |
| PLOT-41 | 1 | 1 |
| PLOT-42 | 1 | 1 |
| PLOT-43 | 1 | 0 |
| PLOT-44 | 1 | 0 |
| LIG-45 | 1 | 0 |
| LIG-46 | 1 | 0 |
| LIG-47 | 1 | 0 |
| LIG-48 | 1 | 1 |
| LIG-49 | 1 | 1 |
| LIG-50 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 63% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2029-08-10 | |
| Revised completion | 2029-12-10 |
Quarterly progress
| 2024-Q3 | 18% |
| 2024-Q4 | 24% |
| 2025-Q1 | 30% |
| 2025-Q2 | 36% |
| 2025-Q3 | 42% |
| 2025-Q4 | 48% |
| 2026-Q1 | 55% |
| 2026-Q2 | 63% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHRI RAM BUILDER AND DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjI0Mg==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities