SHRI SAI VILLAGE
AARTHIK HOUSING LIMITED · Patna
Units48
Booked24 of 48As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2025-12-30Proposed
Registered on2022-03-30
Valid to2025-12-30
Approvals8
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 8 unit types |
| Construction & progress | 4 progress details · 15 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 39 documents · 23 source links |
Registration
Registration
| Promoter | AARTHIK HOUSING LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP40335-6/11/R-1312/2022 | |
| Registered on | 2022-03-30 | |
| Valid to | 2025-12-30 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2025-12-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2022-07-01 | PATNA METROPLOTANT AREA ATHORITY | |
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc. | |||
| Notice of Commencement | |||
| Environment Clearance | 2025-12-31 | ||
| Fire NOC | 2025-12-31 | OFFICE OF THE STATE FIRE OFFICER-CUM-DIRECTOR, BIHAR, PATNA | |
| Airport NOC | 2025-12-31 | AIR PORT AREA AUTHORITY OF INDIA | |
| Water Supply Permission | 2025-12-31 | ||
| Other approval | 2025-12-31 | PATNA METRO POLITANT AREA AUTHORITY |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind |
|---|---|---|
| RERA/CC/375/2025 | RERA Bihar | Complaint |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹52,50,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,771.14 | |
|---|---|---|
| Built-up (m²) | 4,354.31 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 48 | |
| Booked | 24 | |
| Booked as of | 2025-12-31 |
Unit types
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
| 2 BHK | 6 | SHRI SAI VILLAGE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-12-31 | |
| Start | 2022-05-31 | |
| Proposed completion | 2025-12-30 |
Quarterly progress
| 2025-Q4 | 2026-01-29 | 100% | 24 |
| 2025-Q3 | 2025-10-31 | ||
| 2025-Q2 | 2025-07-28 | ||
| 2025-Q1 | 2025-04-20 | ||
| 2024-Q4 | 2025-01-19 | ||
| 2024-Q3 | 2024-10-04 | ||
| 2024-Q2 | 2024-07-04 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2024-07-25 | ||
| 2022-Q4 | 2023-02-03 | ||
| 2022-Q3 | 2022-10-21 | ||
| 2022-Q2 | 2022-07-18 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AARTHIK HOUSING LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 4 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP06042019140335-6
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP06042019140335&ld=pan&pj=RERAP06042019140335-6&f=2025-2026&q=3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP06042019140335-6
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-29
- Quarterly Progress Image · 2025-07-28
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-31
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-28
- Q4-Jan to Mar / 2024-2025 · 2025-04-20
- Q3-Oct to Dec / 2024-2025 · 2025-01-19
- Q2-Jul to Sep / 2024-2025 · 2024-10-04
- Q1-Apr to Jun / 2024-2025 · 2024-07-04
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2023-02-03
- Q2-Jul to Sep / 2022-2023 · 2022-10-21
- Q1-Apr to Jun / 2022-2023 · 2022-07-18
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Other · 2026-06-05 · Sign in to download
- Other · 2026-04-22 · Sign in to download
- Other · 2026-02-06 · Sign in to download
- Other · 2026-08-25 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Notice of Commencement
- 2025-Q3 · 2025-10-31
- 2025-Q2 · 2025-07-28
- 2025-Q1 · 2025-04-20
- 2024-Q4 · 2025-01-19
- 2024-Q3 · 2024-10-04
- 2024-Q2 · 2024-07-04
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2023-02-03
- 2022-Q3 · 2022-10-21
- 2022-Q2 · 2022-07-18