Overview
SHRISTI DURLAV
SHRISTI DEVELOPERS · BHAGATPARA ROAD
Units48
Completion2029-12-31Proposed
Registered on2026-09-02
Valid to2029-12-31
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 7 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 27 documents · 5 source links |
Registration
Registration
| Promoter | SHRISTI DEVELOPERS | |
|---|---|---|
| District | NALBARI | |
| Locality | BHAGATPARA ROAD | |
| Regulator | RERA Assam | |
| Registration number | RERAA NB 286 OF 2026-2027 | |
| Registered on | 2026-09-02 | |
| Valid to | 2029-12-31 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2029-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | ||
| Building Plan | ||
| NOC/Building Permit | NMB/Bld.Per/w-02/2023-24/27765 | 2024-12-02 |
| I. NMB/BLD.PER/W-02/2023-24/27765 | 2024-02-12 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹8,37,28,000 | |
| Total | ₹13,95,47,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,415.68 | |
|---|---|---|
| Units | 48 |
Unit types
| 3 | 95.68 | 6 |
| 3 | 104.05 | 6 |
| 3 | 99.96 | 6 |
| 3 | 97.54 | 6 |
| 3 | 119.37 | 12 |
| 4 | 142.14 | 6 |
| 4 | 143.53 | 6 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-09-01 | |
|---|---|---|
| Proposed completion | 2029-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHRISTI DEVELOPERS | |
|---|---|---|
| Other projects in this city pack | 11 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/2345
- https://rera.assam.gov.in/view_project/searchprojectDetail/2345
- Registration Certificate
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2025-12-30 · Sign in to download
- AUDITED BALANCE SHEET OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2026-01-02 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2026-01-02 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2026-01-02 · Sign in to download
- CASHFLOW STATEMENT · 2026-01-03 · Sign in to download
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2025-12-30 · Sign in to download
- PLAN OF DEVELOPMENT WORKS · 2025-12-30
- COMMENCEMENT CERTIFICATE OF THE PROJECT · 2025-12-30 · Sign in to download
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2025-12-31 · Sign in to download
- PLANNING PERMIT FROM COMPETENT AUTHORITY · 2025-12-31
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2025-12-31 · Sign in to download
- CARPET AREA AND PARKING AREA DETAILS · 2026-01-02 · Sign in to download
- PROJECT COST ESTIMATE · 2026-01-02 · Sign in to download
- FIRE NOC · 2026-01-02
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2026-01-02 · Sign in to download
- Other · 2025-12-30 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2025-12-30
- Other · 2025-12-30 · Sign in to download
- LETTER OF AUTHORIZATION FOR AUTHORIZED SIGNATORY · 2025-12-30 · Sign in to download
- FORM B, DULY NOTARIZED · 2026-01-02 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2025-12-30 · Sign in to download
- POWER OF ATTORNEY · 2025-12-31 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2026-01-02 · Sign in to download
- Project application order/letter · 2026-08-24 · Sign in to download
- Project application order/letter · 2026-06-24 · Sign in to download
- Project application order/letter · 2026-05-25 · Sign in to download