Overview
SHUBH LAXMI PROPERTY & DEVELOPERS
LAXMI NARAYAN SEN · DURG
Units87
Booked39 of 87As of 2025-06-30
Construction progress100%As of 2025-06-30
Completion2027-02-06Proposed
Registered on2022-05-07
Approvals4
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 13 quarters |
| Technical report | |
| Site & area | 3 site details · 87 unit types |
| Construction & progress | 3 progress details · 13 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 88 documents · 10 source links |
Registration
Registration
| Promoter | LAXMI NARAYAN SEN | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA070522001423 | |
| Registered on | 2022-05-07 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2027-02-06 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-COM-2025-03277 | CG RERA | Complaint | Disposed | 2026-07-22 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹19,05,000 | |
|---|---|---|
| Construction | ₹5,35,06,000 |
Quarterly money flows
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹0 |
| 2022-Q4 | ₹12,000 |
| 2023-Q1 | ₹12,001 |
| 2023-Q2 | ₹47,83,105 |
| 2023-Q3 | ₹68,94,585 |
| 2023-Q4 | ₹18,785 |
| 2024-Q1 | ₹1 |
| 2024-Q2 | ₹1 |
| 2024-Q3 | ₹15,33,421 |
| 2024-Q4 | ₹1 |
| 2025-Q1 | ₹7,67,901 |
| 2025-Q2 | ₹1 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 87 | |
|---|---|---|
| Booked | 39 | |
| Booked as of | 2025-06-30 |
Unit types
| Block H -1 | 1 | 1 |
| Block H -2 | 1 | 1 |
| Block H -3 | 1 | 0 |
| Block H -4 | 1 | 0 |
| Block H -5 | 1 | 0 |
| Block H -6 | 1 | 0 |
| Block H -7 | 1 | 1 |
| Block H -8 | 1 | 1 |
| Block H -9 | 1 | 0 |
| Block H -10 | 1 | 0 |
| Block H -11 | 1 | 1 |
| Block H -12 | 1 | 1 |
| Block H -13 | 1 | 0 |
| Block H -14 | 1 | 0 |
| Block H -15 | 1 | 0 |
| Block H -16 | 1 | 0 |
| Block H -17 | 1 | 1 |
| Block H -18 | 1 | 1 |
| Block H -19 | 1 | 1 |
| Block H -20 | 1 | 1 |
| Block H -21 | 1 | 0 |
| Block H -22 | 1 | 0 |
| Block H -23 | 1 | 1 |
| Block H -24 | 1 | 1 |
| Block H -25 | 1 | 0 |
| Block H -26 | 1 | 1 |
| Block H -27 | 1 | 1 |
| Block H -28 | 1 | 1 |
| Block H -29 | 1 | 1 |
| Block H -30 | 1 | 1 |
| Block H -31 | 1 | 1 |
| Block H -32 | 1 | 0 |
| Block H -33 | 1 | 0 |
| Block H -34 | 1 | 0 |
| Block H -35 | 1 | 0 |
| Block H -36 | 1 | 1 |
| Block H -37 | 1 | 0 |
| Block H -38 | 1 | 0 |
| Block H -39 | 1 | 0 |
| Block H -40 | 1 | 1 |
| Block H -41 | 1 | 1 |
| Block H -42 | 1 | 0 |
| Block H -43 | 1 | 0 |
| Block H -44 | 1 | 0 |
| Block H -45 | 1 | 0 |
| Block H -46 | 1 | 0 |
| Block H -47 | 1 | 0 |
| Block H -48 | 1 | 0 |
| Block H -49 | 1 | 0 |
| Block H -50 | 1 | 0 |
| Block H -51 | 1 | 0 |
| Block H -52 | 1 | 1 |
| Block H -53 | 1 | 1 |
| Block H -54 | 1 | 1 |
| Block H -55 | 1 | 1 |
| Block H -56 | 1 | 1 |
| Block H -57 | 1 | 0 |
| Block H -58 | 1 | 0 |
| Block H -59 | 1 | 0 |
| Block H -60 | 1 | 1 |
| Block H -61 | 1 | 1 |
| Block H -62 | 1 | 0 |
| Block H -63 | 1 | 0 |
| Block H -64 | 1 | 1 |
| Block H -65 | 1 | 1 |
| Block H -66 | 1 | 1 |
| Block H -67 | 1 | 1 |
| Block H -68 | 1 | 1 |
| Block LIG-1 | 1 | 1 |
| Block LIG-2 | 1 | 0 |
| Block LIG-3 | 1 | 1 |
| Block LIG-4 | 1 | 1 |
| Block LIG-5 | 1 | 0 |
| Block LIG-6 | 1 | 0 |
| Block LIG-7 | 1 | 0 |
| Block LIG-8 | 1 | 0 |
| Block LIG-9 | 1 | 0 |
| Block LIG-10 | 1 | 0 |
| Block LIG-11 | 1 | 0 |
| Block LIG-12 | 1 | 0 |
| Block LIG-13 | 1 | 0 |
| Block LIG-14 | 1 | 0 |
| Block LIG-15 | 1 | 0 |
| Block LIG-16 | 1 | 1 |
| Block LIG-17 | 1 | 0 |
| Block LIG-18 | 1 | 1 |
| Block LIG-19 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-06-30 | |
| Proposed completion | 2027-02-06 |
Quarterly progress
| 2022-Q2 | 5% |
| 2022-Q3 | 9% |
| 2022-Q4 | 15% |
| 2023-Q1 | 93% |
| 2023-Q2 | 93% |
| 2023-Q3 | 96% |
| 2023-Q4 | 97% |
| 2024-Q1 | 100% |
| 2024-Q2 | 100% |
| 2024-Q3 | 100% |
| 2024-Q4 | 100% |
| 2025-Q1 | 100% |
| 2025-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | LAXMI NARAYAN SEN | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTc0MA==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-07-22 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities
- M-COM-2025-03277 · Sign in to download