SHYAM EXCLUSIVE

INDOWESTERN BUILDTECH LLP · Scheme Shri Ram Vihar C-Block
Units48
Booked17 of 48As of 2024-06-30
Completion2025-02-28Revised · Proposed 2023-09-02
Registered on2023-10-23
Valid to2025-02-28

Sections

Property title & search report
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area7 site details · 14 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details · 1 professional firm
The evidence
Sources28 documents · 6 source links

Registration

Registration

PromoterINDOWESTERN BUILDTECH LLP
DistrictJaipur
LocalityScheme Shri Ram Vihar C-Block
RegulatorRajasthan RERA
Registration numberRAJ/P/2023/2775
Registered on2023-10-23
Valid to2025-02-28
Project typeGroup Housing
Status (as filed)COMPLETED
Proposed completion2023-09-02