Overview
SHYAM SHANTI ESTATES
OMM REALTORS PVT LTD · Patna
Units79
Booked33 of 79As of 2026-09-30
Construction progress89%As of 2026-09-30
Completion2027-10-23Proposed
Registered on2022-12-27
Valid to2027-10-23
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 5 unit types |
| Construction & progress | 4 progress details · 15 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 31 documents · 21 source links |
Registration
Registration
| Promoter | OMM REALTORS PVT LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP84240-1/212/R-1511/2022 | |
| Registered on | 2022-12-27 | |
| Valid to | 2027-10-23 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2027-10-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2022-07-06 | PATNA METROPOLITAN AREA AUTHORITY |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | ||
| Notice of Commencement in form X | ||
| Fire NOC | FIRE NOC (DIRECTOR STATE FIRE SERVICE BIHAR, PATNA) | |
| Airport NOC | GENERAL MANAGER, AIRPORT AUTHORITY OF INDIA, REGIONAL HEAD QUARTER, EASTERN REGION, KOLKATA |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,53,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,898.68 | |
|---|---|---|
| Built-up (m²) | 9,728.93 | |
| FAR | 2.49 | |
| Towers | 3 | |
| Units | 79 | |
| Booked | 33 | |
| Booked as of | 2026-09-30 |
Unit types
| 3 BHK | 30 | BLOCK B |
| 2 BHK | 6 | BLOCK C |
| Convenience Store | 8 | BLOCK A |
| 3 BHK | 28 | BLOCK C |
| 2 BHK | 7 | BLOCK B |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 89% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2022-10-24 | |
| Proposed completion | 2027-10-23 |
Quarterly progress
| 2026-Q3 | 2026-10-26 | 89% | 33 |
| 2026-Q2 | 2026-07-22 | ||
| 2026-Q1 | 2026-04-26 | ||
| 2025-Q4 | 2026-01-21 | ||
| 2025-Q3 | 2025-10-24 | ||
| 2025-Q2 | 2025-07-16 | ||
| 2025-Q1 | 2025-04-14 | ||
| 2024-Q4 | 2025-01-13 | ||
| 2024-Q3 | 2024-10-14 | ||
| 2024-Q2 | 2024-07-14 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-09 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | OMM REALTORS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | INDIAN OVERSEAS BANK | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | SMRITI ARCHITECTS PVT LTD |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP09142022084240-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP09142022084240&ld=pan&pj=RERAP09142022084240-1&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP09142022084240-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-26
- Quarterly Progress Image · 2026-04-26
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-22
- Quarterly Progress Image · 2025-07-16
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-26
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-21
- Quarterly Progress Image · 2026-01-21
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-24
- Quarterly Progress Image · 2025-10-24
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-16
- Q4-Jan to Mar / 2024-2025 · 2025-04-14
- Q3-Oct to Dec / 2024-2025 · 2025-01-13
- Q2-Jul to Sep / 2024-2025 · 2024-10-14
- Q1-Apr to Jun / 2024-2025 · 2024-07-14
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-09
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q2 · 2026-07-22
- 2026-Q1 · 2026-04-26
- 2025-Q4 · 2026-01-21
- 2025-Q3 · 2025-10-24
- 2025-Q2 · 2025-07-16
- 2025-Q1 · 2025-04-14
- 2024-Q4 · 2025-01-13
- 2024-Q3 · 2024-10-14
- 2024-Q2 · 2024-07-14
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-09