Overview
Shyam Shashi Heritage
DHARMENDRA SHASI CONSTRUCTION COMPANY PRIVATE LIMITED · Patna
Units16
Booked16 of 16As of 2026-09-30
Construction progress30%As of 2026-09-30
Completion2029-02-15Proposed
Registered on2025-09-06
Valid to2029-02-15
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 1 unit type |
| Construction & progress | 4 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 13 source links |
Registration
Registration
| Promoter | DHARMENDRA SHASI CONSTRUCTION COMPANY PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP190628070925150229E00 | |
| Registered on | 2025-09-06 | |
| Valid to | 2029-02-15 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-02-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | Danapur Nagar Parisad | |
| Environmental Clearance Certificate | ||
| NOC From Airport Authority of India | ||
| NOC from Fire Service Authority | ||
| Notice of Commencement in form X | ||
| Environment Clearance | 2026-09-30 | |
| Fire NOC | 2029-02-15 | State Fire Officer |
| Airport NOC | 2027-02-15 | |
| Water Supply Permission | 2027-02-15 | Self |
| Other approval | 2029-02-15 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 758.92 | |
|---|---|---|
| Built-up (m²) | 1,892.08 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 16 | |
| Booked | 16 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 16 | Shyam Shashi Heritage |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 30% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2025-06-04 | |
| Proposed completion | 2029-02-15 |
Quarterly progress
| 2026-Q3 | 2026-10-22 | 30% | 16 |
| 2026-Q2 | 2026-09-30 | ||
| 2026-Q1 | 2026-09-30 | ||
| 2025-Q4 | 2026-09-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DHARMENDRA SHASI CONSTRUCTION COMPANY PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP159201800856-3
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP159201800856&ld=pan&pj=RERAP159201800856-3&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP159201800856-3
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- A certificate from a Chartered accountant declaring that no advance booking amount has been taken from the customers against the current project duly signed by the promoter and countersigned by CA · Sign in to download
- Any other Project related documents · Sign in to download
- Declaration (Form B) · Sign in to download
- Environmental Clearance Certificate
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-22
- Quarterly Progress Image · 2026-09-30
- Q1 (Apr - Jun) / 2026-2027 · 2026-09-30
- Q4 (Jan - Mar) / 2025-2026 · 2026-09-30
- Q3 (Oct - Dec) / 2025-2026 · 2026-09-30
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Other · 2026-10-09 · Sign in to download
- Other · 2026-09-24 · Sign in to download
- Environmental Clearance Certificate
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- 2026-Q2 · 2026-09-30
- 2026-Q1 · 2026-09-30
- 2025-Q4 · 2026-09-30