Overview
SHYAM VATIKA PHASE-III PART-A
CHOPRA COLONISERS AND DEVELOPERS PRIVATE LIMITED · Sirsi Road, Sector-49
Units52
Booked40 of 52As of 2024-03-31
Completion2024-11-30Revised · Proposed 2014-03-14
Registered on2022-11-23
Valid to2024-11-30
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 22 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 44 documents · 6 source links |
Registration
Registration
| Promoter | CHOPRA COLONISERS AND DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Locality | Sirsi Road, Sector-49 | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2022/2251 | |
| Registered on | 2022-11-23 | |
| Valid to | 2024-11-30 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2014-03-14 | |
| Revised completion | 2024-11-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,50,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹9,00,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q1 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 12,629.78 | |
|---|---|---|
| Built-up (m²) | 6,850.25 | |
| Towers | 52 | |
| Units | 52 | |
| Booked | 40 | |
| Booked as of | 2024-03-31 |
Unit types
| Plot No. 19 | 1 | 0 |
| Plot No. 20 to 27 | 8 | 0 |
| Plot No. 28 | 1 | 0 |
| Plot No. 29 | 1 | 0 |
| Plot No. 30 to 41 and Plot No. 44 to 54 | 23 | 0 |
| Plot No. 42 and 43 | 2 | 0 |
| Plot No. 55 | 1 | 0 |
| Plot No. 56 | 1 | 0 |
| Plot No. 57 | 1 | 0 |
| Plot No. 58 | 1 | 0 |
| Plot No. 59 | 1 | 0 |
| Plot No. 60 | 1 | 0 |
| Plot No. 61 | 1 | 0 |
| Plot No. 62 | 1 | 0 |
| Plot No. 63 | 1 | 0 |
| Plot No. 64 | 1 | 0 |
| Plot No. 65 | 1 | 0 |
| Plot No. 66 | 1 | 0 |
| Plot No. 67 | 1 | 0 |
| Plot No. 85 | 1 | 0 |
| Plot No. 86 | 1 | 0 |
| Plot No. 87 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2014-03-14 | |
|---|---|---|
| Proposed completion | 2014-03-14 | |
| Revised completion | 2024-11-30 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q1 | 2024-05-08 | 40 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CHOPRA COLONISERS AND DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AU SMALL FINANCE BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=-LOshzu7EMyBNg_LADTt1w
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/-LOshzu7EMyBNg_LADTt1w
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=%2BLOshzu7EMyBNg%2FLADTt1w%3D%3D&QuarterIdEnc=Nj9U%2FLZCLu7pS04J0BaBRA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=r91z8YcVWC4%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2022-11-12
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2022-11-11
- LayoutPlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- SitePlanPath · 2022-11-11
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2024-01-29 · Sign in to download
- R2_UploadDoc · 2024-01-29 · Sign in to download
- R3_UploadedPath · 2024-04-15 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download