Overview
SIDDHIVINAYAK ENCLAVE
MORDERNVILLA CONSTRUCTION INDIA PVT.LTD · Patna
Units162
Completion2021-12-31Proposed
Registered on2018-09-13
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 11 unit types |
| Construction & progress | 2 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 13 source links |
Registration
Registration
| Promoter | MORDERNVILLA CONSTRUCTION INDIA PVT.LTD | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00061-1/97/R-165/2018 | |
| Registered on | 2018-09-13 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2021-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,98,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,768.33 | |
|---|---|---|
| Built-up (m²) | 14,408.55 | |
| FAR | 2.49 | |
| Towers | 3 | |
| Units | 162 |
Unit types
| 2 BHK | 10 | SIDDHIVINAYAK ENCLAVE |
| 3 BHK | 20 | SIDDHIVINAYAK ENCLAVE |
| 3 BHK | 20 | SIDDHIVINAYAK ENCLAVE |
| 3 BHK | 20 | SIDDHIVINAYAK ENCLAVE |
| 2 BHK | 10 | SIDDHIVINAYAK ENCLAVE |
| 2 BHK | 10 | SIDDHIVINAYAK ENCLAVE |
| 3 BHK | 18 | SIDDHIVINAYAK ENCLAVE |
| 3 BHK | 6 | SIDDHIVINAYAK ENCLAVE |
| 2 BHK | 12 | SIDDHIVINAYAK ENCLAVE |
| 2 BHK | 24 | SIDDHIVINAYAK ENCLAVE |
| 2 BHK | 12 | SIDDHIVINAYAK ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-12-01 | |
|---|---|---|
| Proposed completion | 2021-12-31 |
Quarterly progress
| 2021-Q3 | 2021-10-12 |
| 2021-Q2 | 2021-09-20 |
| 2021-Q1 | 2021-07-01 |
| 2020-Q4 | 2021-02-13 |
| 2020-Q3 | 2020-12-22 |
| 2020-Q2 | 2020-12-22 |
| 2020-Q1 | 2020-12-22 |
| 2019-Q4 | 2020-01-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MORDERNVILLA CONSTRUCTION INDIA PVT.LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP3011201700061-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP3011201700061-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2-Jul to Sep / 2021-2022 · 2021-10-12
- Q1-Apr to Jun / 2021-2022 · 2021-09-20
- Q4-Jan to Mar / 2020-2021 · 2021-07-01
- Q3-Oct to Dec / 2020-2021 · 2021-02-13
- Q2-Jul to Sep / 2020-2021 · 2020-12-22
- Q1-Apr to Jun / 2020-2021 · 2020-12-22
- Q4-Jan to Mar / 2019-2020 · 2020-12-22
- Q3-Oct to Dec / 2019-2020 · 2020-01-31
- Project Photogragh · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- 2021-Q3 · 2021-10-12
- 2021-Q2 · 2021-09-20
- 2021-Q1 · 2021-07-01
- 2020-Q4 · 2021-02-13
- 2020-Q3 · 2020-12-22
- 2020-Q2 · 2020-12-22
- 2020-Q1 · 2020-12-22
- 2019-Q4 · 2020-01-31