Overview
SIGNATURE GLOBAL CITY 79B
JMK HOLDINGS PVT. LTD. · Gurugram
Units194
Completion2024-04-30Proposed
Registered on2022-12-23
Valid to2027-04-27
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 8 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 17 documents · 2 source links |
Registration
Registration
| Promoter | JMK HOLDINGS PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/656/388/2022/131 DATED 23.12.2022 | |
| Registered on | 2022-12-23 | |
| Valid to | 2027-04-27 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 100 OF 2022 Dated 25-7-2022 | Town & Country Planning Department | |
| Layout Plan | 2022-10-14 | ||
| Building Plan | |||
| I. LICENSE NO. 100 OF 2022 | 2022-07-25 | ||
| II. FOREST NOC REF. NO. KF4-UJX-Y1Y2 | 2020-07-24 | ||
| III. LAYOUT PLAN MEMO NO. DGDTCP8681 | 2022-10-14 | ||
| IV. ZONING PLAN MEMO NO.DRG.NO. DG,TCP-8682 | 2022-10-14 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,09,80,32,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹1,79,33,48,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1 | |
|---|---|---|
| Units | 194 |
Unit types
| Plot | 118 | |
| Plot | 43 | |
| Plot | 19 | |
| Plot | 4 | |
| Plot | 4 | |
| Plot | 4 | |
| Plot | 2 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-11-01 | |
|---|---|---|
| Proposed completion | 2024-04-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | JMK HOLDINGS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | INDUSIND BANK LIMITED | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2189
- Registration Certificate · 2022-12-23
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2022-11-08 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2022-11-08
- COPIES OF DD · 2022-11-12 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2022-11-09
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2022-11-08
- DEMARCATION PLAN · 2022-11-08
- ZONING PLAN · 2022-11-08
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2022-11-08 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2022-11-09
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2022-11-10 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2022-11-10
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2022-11-14 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2023-07-04 · Sign in to download
- Extension No. 15 of 2025 dated 28.03.2025 · 2025-03-31 · Sign in to download
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/131 of 2022/7(3)/74/2025/16 DATED 05.06.2025 · 2025-06-13 · Sign in to download
- PROJECT CONTINUATION-RC/REP/HARERA/GGM/131 of 2022/7(3)/74/2025/16 dated 22.07.2026 · 2026-07-23 · Sign in to download