Overview
SIGNATURE GLOBAL CITY 92
SIGNATURE INFRBUILD PVT. LTD. · Gurugram
Units191
Completion2023-04-30Proposed
Registered on2021-07-27
Valid to2026-04-27
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 24 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 28 documents · 3 source links |
Registration
Registration
| Promoter | SIGNATURE INFRBUILD PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/470/202/2021/38 DATED 27.07.2021 | |
| Registered on | 2021-07-27 | |
| Valid to | 2026-04-27 | |
| Status (as filed) | Registered | |
| Proposed completion | 2023-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 12 of 2021 dated 12.03.2021 Endst. No. LC-4248/Asstt.(MS)/2021/6671 Dated 15/03/2021 | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. LICENSE APPROVAL 12 OF 2021 | 2021-03-12 | ||
| II. ZONING PLAN APPROVAL DRG. NO. DTCP7738 | 2021-04-20 | ||
| III. WATER SUPPLY MEMO NO. 198 | 2021-04-08 | ||
| IV. SEWAGE DISPOSAL GMDA/SEW/2021/395 | 2021-03-25 | ||
| V. STP TREATED WATER GMDA/SEW/2021/397 | 2021-03-25 | ||
| VI. ELECTRICAL LOAD AVAILABILITY CH.141/DRG.-PLC | 2021-04-03 | ||
| VII. FOREST NOC JFV-QFK-Y5YP & JT8-DAD-BE2T | 2020-11-13 | ||
| VIII. LAYOUT PLAN DTCP- | 2021-03-12 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹54,40,91,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹1,07,54,28,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1 | |
|---|---|---|
| Units | 191 |
Unit types
| Plot | 15 | |
| Plot | 54 | |
| Plot | 26 | |
| Plot | 41 | |
| Plot | 37 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-05-01 | |
|---|---|---|
| Proposed completion | 2023-04-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SIGNATURE INFRBUILD PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LIMITED | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1618
- https://nominatim.openstreetmap.org/search?q=sector+92%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2021-07-27
- DEMARCATION PLAN · 2021-05-10
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-05-10
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-05-10
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2021-05-10 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-05-10
- ZONING PLAN · 2021-05-10
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-05-10
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-05-10 · Sign in to download
- STROM WATER DRAINAGE · 2021-05-11 · Sign in to download
- WATER SUPPLY PLAN · 2021-05-11
- SEWERAGE AND GARBAGE DISPOSAL PLAN · 2021-05-11
- WATER NOC · 2021-05-11
- SEWERAGE NOC · 2021-05-11
- STP NOC · 2021-05-11
- POWER NOC · 2021-05-11
- IRRIGATION PLAN · 2021-05-11
- FOREST NOC MEVKA · 2021-05-11
- FOREST NOC WAZIRPUR · 2021-05-11
- BBA · 2021-05-13 · Sign in to download
- BR RERA ACCOUNT · 2021-05-11 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2021-05-12 · Sign in to download
- ALLOTMENT LETTER · 2021-05-13 · Sign in to download
- APPLICATION FORM · 2021-05-13 · Sign in to download
- Extension No. 13 of 2023 dated 19.06.2023 · 2023-07-05 · Sign in to download
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/38 OF 2021/7(3)/54/2024/13 DATED 08.08.2024 · 2024-08-23 · Sign in to download
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/38 of 2021/7(3)/54/2024/13 DATED 13.08.2025 · 2025-08-18 · Sign in to download
- Completion certificate uploaded · 2026-08-04 · Sign in to download