Overview
SIGNATURE GLOBAL PARK-1(1)
SIGNATUREGLOBAL HOMES PRIVATE LIMITED · Gurugram
Units181
Completion2024-10-31Proposed
Registered on2021-10-11
Valid to2026-10-29
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 3 source links |
Registration
Registration
| Promoter | SIGNATUREGLOBAL HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/494/226/2021/62 DATED 11.10.2021 | |
| Registered on | 2021-10-11 | |
| Valid to | 2026-10-29 | |
| Status (as filed) | Registered | |
| Proposed completion | 2024-10-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 18 of 2021 Dated 16-04-2021 | Town & Country Planning Department | |
| Layout Plan | 2021-04-20 | ||
| Building Plan | 2021-08-31 | ||
| I. LICENSE APPROVAL | 2021-08-16 | ||
| II. BR-III FOR RESIDENTIAL | 2021-08-31 | ||
| III. ENVIRONMENT CLEARANCE APPROVAL BASED ON LATEST APPROVED BUILDING PLAN | 2021-07-09 | ||
| IV. BR-III FOR COMMERCIAL | 2021-09-09 | ||
| V. SERVICE PLAN | 2021-08-12 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹17,40,88,000 | |
|---|---|---|
| Construction | ₹43,00,00,000 | |
| Total | ₹86,61,67,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 2.64 | |
|---|---|---|
| Units | 181 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 5,016 | 60 |
| Apartment/Shops/Other Buildings | 4,681.6 | 56 |
| Apartment/Shops/Other Buildings | 719.41 | 65 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-11-01 | |
|---|---|---|
| Proposed completion | 2024-10-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SIGNATUREGLOBAL HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | SBM BANK LIMITED | |
| Other projects in this city pack | 14 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1707
- https://nominatim.openstreetmap.org/search?q=sector+36%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2021-10-11
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-08-31
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-08-31 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-08-31
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2021-08-31 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-08-31
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-10-05
- BUILDING PLAN 1 · 2021-10-05
- BUILDING PLAN 2 · 2021-10-05
- DOMESTIC WATER SUPPLY LAYOUT · 2021-10-05 · Sign in to download
- DRAINAGE LAYOUT · 2021-10-05 · Sign in to download
- FLUSHING WATER SUPPLY LAYOUT · 2021-10-05 · Sign in to download
- GARDEN HYDRANT LAYOUT · 2021-10-05 · Sign in to download
- ROAD LAYOUT · 2021-10-05 · Sign in to download
- SEWERAGE LAYOUT · 2021-10-05 · Sign in to download
- EXTERNAL DEVELOPMENT WORKS DESIGN AND COST ESTIMATES · 2021-10-05 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2021-10-05
- COMMERCIAL SITE PLAN · 2021-10-05
- DEMARCATION PLAN · 2021-10-05
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2021-10-05 · Sign in to download
- ZONING PLAN · 2021-10-05
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2021-10-05 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2021-10-05 · Sign in to download
- Extension No. 29 of 2024 dated 19.12.2024 · 2024-12-23 · Sign in to download
- Approval for change of bank account · 2025-05-20
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/62 of 2021/7(3)/86/2025/28 DATED 30.10.2025 · 2025-10-21 · Sign in to download