Overview
Signature Green City
KDM SURYACON DEVELOPERS · Fazilka
Units1
Completion2029-09-11Proposed
Valid to2029-09-11
Approvals14
Sections
| Property title & search report | |
|---|---|
| Approvals | 14 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 36 documents · 23 source links |
Registration
Registration
| Promoter | KDM SURYACON DEVELOPERS | |
|---|---|---|
| District | Fazilka | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-FZL19-PR1200 | |
| Valid to | 2029-09-11 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-09-11 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| License as Promoter from competent Authority | 2024-08-01 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from NHAI/ PWD | 2025-04-22 | |
| Other Document (Affidavit Cum Declaration of Noc) | Legal Documents (Received) | 2024-12-28 |
| Other Document (Noc Drainage) | 2024-11-29 | |
| Other Document (NOC FOREST) | 2025-05-05 | |
| Other Document (Noc from Forest Department) | Clearances (Received) | 2025-05-27 |
| Other Document (NOC KHAl) | 2024-05-08 | |
| Other Document (NOC PSPCL Receipt and Application Form) | 2025-01-30 | |
| Other Document (sewerage noc) | 2025-02-18 | |
| Pollution Clearance from Punjab Pollution Control Board | Clearances (Received) | 2025-03-07 |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹8,56,73,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 44,717.74 | |
|---|---|---|
| Units | 1 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| ECONOMIC WEAKER SECTION | 2,217.5 | 1 | EWS AREA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-09-12 | |
|---|---|---|
| Proposed completion | 2029-09-11 |
Quarterly progress
| 2025-Q2 | 2025-08-22 |
| 2025-Q3 | 2025-10-14 |
| 2025-Q4 | 2026-01-15 |
| 2026-Q1 | 2026-04-12 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KDM SURYACON DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12149&inPromoter_ID=3049&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License as Promoter from competent Authority · 2024-08-01
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2025-04-22
- Other Document (Noc Drainage) · 2024-11-29
- Other Document (NOC FOREST) · 2025-05-05
- Other Document (Noc from Forest Department) · 2025-05-27
- Other Document (NOC KHAl) · 2024-05-08
- Other Document (NOC PSPCL Receipt and Application Form) · 2025-01-30
- Other Document (sewerage noc) · 2025-02-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-07
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- License as Promoter from competent Authority · 2024-08-01
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2025-04-22
- Other Document (Affidavit Cum Declaration of Noc) · 2024-12-28
- Other Document (Noc Drainage) · 2024-11-29
- Other Document (NOC FOREST) · 2025-05-05
- Other Document (Noc from Forest Department) · 2025-05-27
- Other Document (NOC KHAl) · 2024-05-08
- Other Document (NOC PSPCL Receipt and Application Form) · 2025-01-30
- Other Document (sewerage noc) · 2025-02-18
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-07
- Consent details of actual owner of Land
- 2025-Q2 · 2025-08-22
- 2025-Q3 · 2025-10-14
- 2025-Q4 · 2026-01-15
- 2026-Q1 · 2026-04-12
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-11