Overview
Silver Coast
Sarvodaya Grih Nirman Pvt. Ltd. · Patna
Units182
Completion2020-03-31Proposed
Registered on2023-01-27
Approvals2
Cases9
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 9 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 28 unit types |
| Construction & progress | 2 progress details · 18 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 52 documents · 34 source links |
Registration
Registration
| Promoter | Sarvodaya Grih Nirman Pvt. Ltd. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00130-1/324/R-286/2018 | |
| Registered on | 2023-01-27 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2020-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA/CC-448/2021 | RERA Bihar | ||
| RERA/CC-462/2021 | RERA Bihar | ||
| RERA/CC-468/2021 | RERA Bihar | ||
| RERA/CC-329/2019 | RERA Bihar | ||
| RERA/CC-330/2019 | RERA Bihar | ||
| RERA/CC-331/2019 | RERA Bihar | ||
| RERA/CC/468/2022 | RERA Bihar | Complaint | Pending |
| Exe. Case No. 449/2022 RERA/CC/449/2021 | RERA Bihar | Complaint | Pending |
| RERA/CC/541(A)/2022 | RERA Bihar | Complaint |
Complaints & cases
| Cases | 9 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,50,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 12,097.94 | |
|---|---|---|
| Built-up (m²) | 28,505.59 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 182 |
Unit types
| Duplex | 1 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 4 BHK | 12 | Silver Coast |
| 2 BHK | 12 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 2 BHK | 12 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 4 BHK | 12 | Silver Coast |
| 3 BHK | 12 | Silver Coast |
| 4 BHK | 12 | Silver Coast |
| 4 BHK | 12 | Silver Coast |
| 4 BHK | 12 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
| Duplex | 1 | Silver Coast |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-04-01 | |
|---|---|---|
| Proposed completion | 2020-03-31 |
Quarterly progress
| 2025-Q1 | 2025-04-15 |
| 2024-Q4 | 2025-01-15 |
| 2024-Q3 | 2024-10-11 |
| 2024-Q2 | 2024-07-13 |
| 2024-Q1 | 2024-07-25 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-10 |
| 2022-Q4 | 2023-01-06 |
| 2022-Q3 | 2022-10-10 |
| 2022-Q2 | 2022-07-08 |
| 2022-Q1 | 2022-04-16 |
| 2021-Q3 | 2021-09-30 |
| 2021-Q1 | 2021-06-17 |
| 2020-Q4 | 2022-01-12 |
| 2020-Q3 | 2020-10-19 |
| 2020-Q2 | 2021-07-05 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Sarvodaya Grih Nirman Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP241201800130-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP241201800130-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-11
- Q1-Apr to Jun / 2024-2025 · 2024-07-13
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-10
- Q3-Oct to Dec / 2022-2023 · 2023-01-06
- Q2-Jul to Sep / 2022-2023 · 2022-10-10
- Q1-Apr to Jun / 2022-2023 · 2022-07-08
- Q4-Jan to Mar / 2021-2022 · 2022-04-16
- Q2-Jul to Sep / 2021-2022 · 2021-09-30
- Q4-Jan to Mar / 2020-2021 · 2021-06-17
- Q3-Oct to Dec / 2020-2021 · 2022-01-12
- Q2-Jul to Sep / 2020-2021 · 2020-10-19
- Q1-Apr to Jun / 2020-2021 · 2021-07-05
- View · 2022-06-09 · Sign in to download
- View · 2022-06-09 · Sign in to download
- View · 2022-06-09 · Sign in to download
- View · 2022-08-18 · Sign in to download
- View · 2022-08-18 · Sign in to download
- View · 2022-08-18 · Sign in to download
- View · 2023-09-15 · Sign in to download
- View · 2024-01-29 · Sign in to download
- View · 2026-02-11 · Sign in to download
- Project Photogragh · Sign in to download
- Other · 2026-02-03 · Sign in to download
- Other · 2022-08-18 · Sign in to download
- Other · 2022-08-18 · Sign in to download
- Other · 2022-08-18 · Sign in to download
- Other · 2022-06-09 · Sign in to download
- Other · 2022-06-09 · Sign in to download
- Other · 2022-06-09 · Sign in to download
- Other · 2022-06-09 · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- RERA/CC-448/2021 · Sign in to download
- RERA/CC-462/2021 · Sign in to download
- RERA/CC-468/2021 · Sign in to download
- RERA/CC-329/2019 · Sign in to download
- RERA/CC-330/2019 · Sign in to download
- RERA/CC-331/2019 · Sign in to download
- RERA/CC/468/2022 · Sign in to download
- Exe. Case No. 449/2022 RERA/CC/449/2021 · Sign in to download
- RERA/CC/541(A)/2022 · Sign in to download
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-11
- 2024-Q2 · 2024-07-13
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-10
- 2022-Q4 · 2023-01-06
- 2022-Q3 · 2022-10-10
- 2022-Q2 · 2022-07-08
- 2022-Q1 · 2022-04-16
- 2021-Q3 · 2021-09-30
- 2021-Q1 · 2021-06-17
- 2020-Q4 · 2022-01-12
- 2020-Q3 · 2020-10-19
- 2020-Q2 · 2021-07-05