Overview
SINDHU
BHUVANESH CONSTRUCTIONS AND DEVELOPERS · Chittoor
Units113
Completion2027-05-26Proposed
Registered on2021-08-13
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 113 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details · 1 professional firm |
| The evidence | |
| Sources | 24 documents · 9 source links |
Registration
Registration
| Promoter | BHUVANESH CONSTRUCTIONS AND DEVELOPERS | |
|---|---|---|
| District | Chittoor | |
| Regulator | AP RERA | |
| Registration number | P10260141790 | |
| Registered on | 2021-08-13 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-05-26 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1166/0053/B/TPTYMDL/TRCHNR/2021 | 2021-05-26 | Vice Chairman,UDA |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,68,59,150 | |
|---|---|---|
| Construction | ₹29,31,21,682 | |
| Total | ₹35,99,80,832 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,510.6 | |
|---|---|---|
| Built-up (m²) | 17,026.12 | |
| Towers | 1 | |
| Units | 113 |
Unit types
| 3BHK | 82.57 | 1 | SINDHU | Fifth floor |
| 2BHK | 73.02 | 1 | SINDHU | Fifth floor |
| 3BHK | 89.64 | 1 | SINDHU | Fifth floor |
| 3BHK | 97.03 | 1 | SINDHU | Fifth floor |
| 2BHK | 71.4 | 1 | SINDHU | Fifth floor |
| 2BHK | 71.4 | 1 | SINDHU | Fifth floor |
| 3BHK | 98.3 | 1 | SINDHU | Fifth floor |
| 3BHK | 98.91 | 1 | SINDHU | Fifth floor |
| 2BHK | 72.66 | 1 | SINDHU | Fifth floor |
| 3BHK | 83.58 | 1 | SINDHU | Fifth floor |
| 2BHK | 75.24 | 1 | SINDHU | Fifth floor |
| 2BHK | 75.23 | 1 | SINDHU | Fifth floor |
| 2BHK | 72.36 | 1 | SINDHU | Fifth floor |
| 2BHK | 66.7 | 1 | SINDHU | Fifth floor |
| 3BHK | 85 | 1 | SINDHU | Fifth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fifth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fifth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fifth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fifth floor |
| 3BHK | 85 | 1 | SINDHU | First floor |
| 2BHK | 69.66 | 1 | SINDHU | First floor |
| 2BHK | 69.66 | 1 | SINDHU | First floor |
| 2BHK | 69.66 | 1 | SINDHU | First floor |
| 2BHK | 69.66 | 1 | SINDHU | First floor |
| 3BHK | 82.57 | 1 | SINDHU | First floor |
| 2BHK | 73.02 | 1 | SINDHU | First floor |
| 3BHK | 89.64 | 1 | SINDHU | First floor |
| 3BHK | 97.03 | 1 | SINDHU | First floor |
| 2BHK | 71.4 | 1 | SINDHU | First floor |
| 2BHK | 71.4 | 1 | SINDHU | First floor |
| 3BHK | 98.3 | 1 | SINDHU | First floor |
| 3BHK | 98.91 | 1 | SINDHU | First floor |
| 2BHK | 72.66 | 1 | SINDHU | First floor |
| 3BHK | 83.58 | 1 | SINDHU | First floor |
| 2BHK | 75.24 | 1 | SINDHU | First floor |
| 2BHK | 75.23 | 1 | SINDHU | First floor |
| 2BHK | 72.36 | 1 | SINDHU | First floor |
| 2BHK | 66.7 | 1 | SINDHU | First floor |
| 3BHK | 85 | 1 | SINDHU | Fourth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fourth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fourth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fourth floor |
| 2BHK | 69.66 | 1 | SINDHU | Fourth floor |
| 3BHK | 82.57 | 1 | SINDHU | Fourth floor |
| 2BHK | 73.02 | 1 | SINDHU | Fourth floor |
| 3BHK | 89.64 | 1 | SINDHU | Fourth floor |
| 3BHK | 97.03 | 1 | SINDHU | Fourth floor |
| 2BHK | 71.4 | 1 | SINDHU | Fourth floor |
| 2BHK | 71.4 | 1 | SINDHU | Fourth floor |
| 3BHK | 98.3 | 1 | SINDHU | Fourth floor |
| 3BHK | 98.91 | 1 | SINDHU | Fourth floor |
| 2BHK | 72.66 | 1 | SINDHU | Fourth floor |
| 3BHK | 83.58 | 1 | SINDHU | Fourth floor |
| 2BHK | 75.24 | 1 | SINDHU | Fourth floor |
| 2BHK | 75.23 | 1 | SINDHU | Fourth floor |
| 2BHK | 72.36 | 1 | SINDHU | Fourth floor |
| 2BHK | 66.7 | 1 | SINDHU | Fourth floor |
| 3BHK | 85 | 1 | SINDHU | Ground floor |
| 2BHK | 69.66 | 1 | SINDHU | Ground floor |
| 2BHK | 69.66 | 1 | SINDHU | Ground floor |
| 2BHK | 69.66 | 1 | SINDHU | Ground floor |
| 2BHK | 69.66 | 1 | SINDHU | Ground floor |
| 3BHK | 82.57 | 1 | SINDHU | Ground floor |
| 2BHK | 73.02 | 1 | SINDHU | Ground floor |
| 3BHK | 89.64 | 1 | SINDHU | Ground floor |
| 3BHK | 97.03 | 1 | SINDHU | Ground floor |
| 2BHK | 71.4 | 1 | SINDHU | Ground floor |
| 2BHK | 71.4 | 1 | SINDHU | Ground floor |
| 3BHK | 98.3 | 1 | SINDHU | Ground floor |
| 3BHK | 98.91 | 1 | SINDHU | Ground floor |
| 2BHK | 72.66 | 1 | SINDHU | Ground floor |
| 2BHK | 75.24 | 1 | SINDHU | Ground floor |
| 2BHK | 75.23 | 1 | SINDHU | Ground floor |
| 2BHK | 72.36 | 1 | SINDHU | Ground floor |
| 2BHK | 66.7 | 1 | SINDHU | Ground floor |
| 3BHK | 85 | 1 | SINDHU | Second floor |
| 2BHK | 69.66 | 1 | SINDHU | Second floor |
| 2BHK | 69.66 | 1 | SINDHU | Second floor |
| 2BHK | 69.66 | 1 | SINDHU | Second floor |
| 2BHK | 69.66 | 1 | SINDHU | Second floor |
| 3BHK | 82.57 | 1 | SINDHU | Second floor |
| 2BHK | 73.02 | 1 | SINDHU | Second floor |
| 3BHK | 89.64 | 1 | SINDHU | Second floor |
| 3BHK | 97.03 | 1 | SINDHU | Second floor |
| 2BHK | 71.4 | 1 | SINDHU | Second floor |
| 2BHK | 71.4 | 1 | SINDHU | Second floor |
| 3BHK | 98.3 | 1 | SINDHU | Second floor |
| 3BHK | 98.91 | 1 | SINDHU | Second floor |
| 2BHK | 72.66 | 1 | SINDHU | Second floor |
| 3BHK | 83.58 | 1 | SINDHU | Second floor |
| 2BHK | 75.24 | 1 | SINDHU | Second floor |
| 2BHK | 75.23 | 1 | SINDHU | Second floor |
| 2BHK | 72.36 | 1 | SINDHU | Second floor |
| 2BHK | 66.7 | 1 | SINDHU | Second floor |
| 3BHK | 85 | 1 | SINDHU | Third floor |
| 2BHK | 69.66 | 1 | SINDHU | Third floor |
| 2BHK | 69.66 | 1 | SINDHU | Third floor |
| 2BHK | 69.66 | 1 | SINDHU | Third floor |
| 2BHK | 69.66 | 1 | SINDHU | Third floor |
| 3BHK | 82.57 | 1 | SINDHU | Third floor |
| 2BHK | 73.02 | 1 | SINDHU | Third floor |
| 3BHK | 89.64 | 1 | SINDHU | Third floor |
| 3BHK | 97.03 | 1 | SINDHU | Third floor |
| 2BHK | 71.4 | 1 | SINDHU | Third floor |
| 2BHK | 71.4 | 1 | SINDHU | Third floor |
| 3BHK | 98.3 | 1 | SINDHU | Third floor |
| 3BHK | 98.91 | 1 | SINDHU | Third floor |
| 2BHK | 72.66 | 1 | SINDHU | Third floor |
| 3BHK | 83.58 | 1 | SINDHU | Third floor |
| 2BHK | 75.24 | 1 | SINDHU | Third floor |
| 2BHK | 75.23 | 1 | SINDHU | Third floor |
| 2BHK | 72.36 | 1 | SINDHU | Third floor |
| 2BHK | 66.7 | 1 | SINDHU | Third floor |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-05-26 | |
|---|---|---|
| Proposed completion | 2027-05-26 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BHUVANESH CONSTRUCTIONS AND DEVELOPERS | |
|---|---|---|
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| CA | M.M.GOPALACHARI MMGS ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFV0cjC7dMA+Aj97bP/C/P69pQU8AF6QvK29Kxs8dF+5KCKDF9P6xppoMwlxy1UtxQVMqZUFX+3o3WbMA4ClV6L/UmAy5d5cRy4vFGc5SIx+w
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE