Overview
SIRIMANE ENCLAVE
SIRIMANE BUILDERS · Davangere
Completion2030-12-31Proposed
Registered on2025-09-10
Valid to2030-12-31
Approvals8
Complaints0
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 5 site details · 56 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 92 documents · 11 source links |
Registration
Registration
| Promoter | SIRIMANE BUILDERS | |
|---|---|---|
| District | Davangere | |
| Regulator | K-RERA | |
| Registration number | PRM/KA/RERA/1258/405/PR/100925/008081 | |
| Registered on | 2025-09-10 | |
| Valid to | 2030-12-31 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | APPROVED | |
| Proposed completion | 2030-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approved Plan | HRH-LBPAS-10589/23-24/BP | 2023-08-14 | Davanagere-Harihara Urban Development Authority |
| Commencement Certificate ( Annexure - 80 ) | |||
| NOC in case of building proposals abutting to neighbouring properties ( Annexure - 104 ) | |||
| AFFIDAVIT - FOR SUBMISSION of NOCs - SIRIMANE | |||
| BESCOM NOC | |||
| Electricity NOC Connection | |||
| KSPCB NOC CFE | |||
| Water NOC Connection |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,30,00,000 | |
|---|---|---|
| Construction | ₹17,70,00,000 | |
| Total | ₹22,00,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,654 | |
|---|---|---|
| Built-up (m²) | 10,608 | |
| FAR | 1.83 | |
| Towers | 1 | |
| Maximum floors | 3 |
Unit types
| 2 BHK | 2,238 | 24 | ||
| 3 BHK | 3,814 | 32 | ||
| 3 BHK | 1 | SIRIMANE ENCLAVE | ||
| 3 BHK | 1 | SIRIMANE ENCLAVE | ||
| 3 BHK | 2 | SIRIMANE ENCLAVE | ||
| 2 BHK | 2 | SIRIMANE ENCLAVE | ||
| 2 BHK | 1 | SIRIMANE ENCLAVE | ||
| 2 BHK | 3 | SIRIMANE ENCLAVE | ||
| 3 BHK | 1 | SIRIMANE ENCLAVE | ||
| 3 BHK | 2 | SIRIMANE ENCLAVE | ||
| 3 BHK | 1 | SIRIMANE ENCLAVE | ||
| 3 BHK | 3 | SIRIMANE ENCLAVE | ||
| 3 BHK | 6 | SIRIMANE ENCLAVE | ||
| 3 BHK | 3 | SIRIMANE ENCLAVE | ||
| 2 BHK | 6 | SIRIMANE ENCLAVE | ||
| 2 BHK | 3 | SIRIMANE ENCLAVE | ||
| 2 BHK | 9 | SIRIMANE ENCLAVE | ||
| 3 BHK | 3 | SIRIMANE ENCLAVE | ||
| 3 BHK | 6 | SIRIMANE ENCLAVE | ||
| 3 BHK | 3 | SIRIMANE ENCLAVE | ||
| 3 BHK | 1 | SIRIMANE ENCLAVE | 0 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 0 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 0 | |
| 2 BHK | 2 | SIRIMANE ENCLAVE | 0 | |
| 2 BHK | 1 | SIRIMANE ENCLAVE | 0 | |
| 2 BHK | 3 | SIRIMANE ENCLAVE | 0 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 0 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 0 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 0 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 1 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 1 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 1 | |
| 2 BHK | 2 | SIRIMANE ENCLAVE | 1 | |
| 2 BHK | 1 | SIRIMANE ENCLAVE | 1 | |
| 2 BHK | 3 | SIRIMANE ENCLAVE | 1 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 1 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 1 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 1 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 2 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 2 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 2 | |
| 2 BHK | 2 | SIRIMANE ENCLAVE | 2 | |
| 2 BHK | 1 | SIRIMANE ENCLAVE | 2 | |
| 2 BHK | 3 | SIRIMANE ENCLAVE | 2 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 2 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 2 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 2 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 3 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 3 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 3 | |
| 2 BHK | 2 | SIRIMANE ENCLAVE | 3 | |
| 2 BHK | 1 | SIRIMANE ENCLAVE | 3 | |
| 2 BHK | 3 | SIRIMANE ENCLAVE | 3 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 3 | |
| 3 BHK | 2 | SIRIMANE ENCLAVE | 3 | |
| 3 BHK | 1 | SIRIMANE ENCLAVE | 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-01-01 | |
|---|---|---|
| Proposed completion | 2030-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SIRIMANE BUILDERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://mahitikanaja.karnataka.gov.in/Rera/api/Rera/ProjectViewDetails
- https://rera.karnataka.gov.in/projectDetails
- https://rera.karnataka.gov.in/projectViewDetails
- https://rera.karnataka.gov.in/viewAllProjects?language=en
- Registration Certificate ( Annexure - 1 )
- Other · Sign in to download
- GST Certificate ( Annexure - 3 ) · Sign in to download
- Other · Sign in to download
- Board Resolution for Authorized Signatory/Certificate of Authorization ( Annexure - 5 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Certificate issued by CA Form 1 ( Annexure - 59 ) · Sign in to download
- Certificate issued by Architect Form 2 ( Annexure - 60 ) · Sign in to download
- Certificate issued by Engineer Form 3 ( Annexure - 61 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Balance Sheet ( Annexure - 70 ) · Sign in to download
- Balance Sheet ( Annexure - 70 ) · Sign in to download
- Balance Sheet ( Annexure - 70 ) · Sign in to download
- Audited Profit and Loss Statement ( Annexure - 71 ) · Sign in to download
- Audited Profit and Loss Statement ( Annexure - 71 ) · Sign in to download
- Audited Profit and Loss Statement ( Annexure - 71 ) · Sign in to download
- Income Tax Return Acknowledgement ( Annexure - 72 ) · Sign in to download
- Income Tax Return Acknowledgement ( Annexure - 72 ) · Sign in to download
- Income Tax Return Acknowledgement ( Annexure - 72 ) · Sign in to download
- Commencement Certificate ( Annexure - 80 )
- Approved Building Plan ( Annexure - 81 )
- Sectional Drawing of the apartments ( Annexure - 82 )
- Certificate from Registered Engineer indicating the structural safety of the building ( Annexure - 83 ) · Sign in to download
- Project Specifications ( Annexure - 84 ) · Sign in to download
- Brochure ( Annexure - 85 ) · Sign in to download
- Declaration (Form B) ( Annexure - 89 ) · Sign in to download
- Advocate Search Report ( Annexure - 92 ) · Sign in to download
- ESCOM/Electricity ( Annexure - 95 ) · Sign in to download
- KWSSB/Water ( Annexure - 96 ) · Sign in to download
- KSPCB ( Annexure - 97 ) · Sign in to download
- SEIAA ( Annexure - 98 ) · Sign in to download
- Fire Force Department ( Annexure - 99 ) · Sign in to download
- Airport Authority of India ( Annexure - 100 ) · Sign in to download
- BSNL ( Annexure - 101 ) · Sign in to download
- Lift Authorities ( Annexure - 102 ) · Sign in to download
- BMRCL ( Annexure - 103 ) · Sign in to download
- NOC in case of building proposals abutting to neighbouring properties ( Annexure - 104 )
- Bangalore Urban Arts Commission ( Annexure - 105 ) · Sign in to download
- Inspector Of Factories Controller Of Explosives Railways ( Annexure - 106 ) · Sign in to download
- Coastal Regulation Zone Authority ( Annexure - 107 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Document ( Annexure - 113 ) · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · 2025-09-04 · Sign in to download
- Amenities & Facilities & Infrastructures signed by Engineer - SIRIMANE · 2025-09-04 · Sign in to download
- APPROVED Plan copy - Sirimane · 2025-09-04
- APPROVED Plan Licence copy - Sirimane · 2025-09-04
- BESCOM NOC · 2025-09-04
- Other · 2025-09-04 · Sign in to download
- Other · 2025-09-04 · Sign in to download
- Electricity NOC Connection · 2025-09-04
- Other · 2025-09-04 · Sign in to download
- Other · 2025-09-04 · Sign in to download
- KSPCB NOC CFE · 2025-09-04
- Other · 2025-09-04 · Sign in to download
- Other · 2025-09-04 · Sign in to download
- Pre-Stability Certificate - SIRIMANE_signed copy · 2025-09-04 · Sign in to download
- Sources of Funds · 2025-09-04 · Sign in to download
- Other · 2025-09-04 · Sign in to download
- Ver 01_ALLOTMENT LETTER - SIRIMANE · 2025-09-04 · Sign in to download
- Other · 2025-09-04 · Sign in to download
- Water NOC Connection · 2025-09-04
- Other · 2025-09-04 · Sign in to download
- Registration certificate
- Registration Certificate
- Commencement Certificate ( Annexure - 80 )
- NOC in case of building proposals abutting to neighbouring properties ( Annexure - 104 )
- AFFIDAVIT - FOR SUBMISSION of NOCs - SIRIMANE
- BESCOM NOC
- Electricity NOC Connection
- KSPCB NOC CFE
- Water NOC Connection