Overview
SKK VALENCIA, ALIAS EXPRESSION VALENCIA
Shanti Krishna Kanhaiya Construction and Developers Pvt.Ltd · Patna
Units236
Booked44 of 236As of 2026-06-30
Construction progress56%As of 2026-06-30
Completion2027-03-29Proposed
Registered on2022-04-13
Valid to2027-03-29
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 6 unit types |
| Construction & progress | 4 progress details · 17 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 23 source links |
Registration
Registration
| Promoter | Shanti Krishna Kanhaiya Construction and Developers Pvt.Ltd | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP95037-1/44/R-1376/2022 | |
| Registered on | 2022-04-13 | |
| Valid to | 2027-03-29 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2027-03-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc. | ||
| Notice of Commencement | ||
| Environment Clearance | 2029-03-29 | STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY |
| Fire NOC | 2027-03-29 | BIHAR FIRE SERVICE |
| Airport NOC | 2027-03-29 | AIRPORT AUTHORITY OF INDIA |
| Water Supply Permission | 2027-03-29 | DEPARTMENT OF WATER RESOURCES |
| Other approval | 2027-03-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹9,10,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,914.71 | |
|---|---|---|
| Built-up (m²) | 24,697.26 | |
| FAR | 2.49 | |
| Towers | 5 | |
| Units | 236 | |
| Booked | 44 | |
| Booked as of | 2026-06-30 |
Unit types
| 4 BHK | 47 | SKK VALENCIA, ALIAS EXPRESSION VALENCIA |
| 3 BHK | 46 | SKK VALENCIA, ALIAS EXPRESSION VALENCIA |
| 1 BHK | 27 | SKK VALENCIA, ALIAS EXPRESSION VALENCIA |
| 2 BHK | 24 | SKK VALENCIA, ALIAS EXPRESSION VALENCIA |
| 3 BHK | 46 | SKK VALENCIA, ALIAS EXPRESSION VALENCIA |
| 3 BHK | 46 | SKK VALENCIA, ALIAS EXPRESSION VALENCIA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 56% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2022-03-30 | |
| Proposed completion | 2027-03-29 |
Quarterly progress
| 2026-Q2 | 2026-08-22 | 56% | 44 |
| 2026-Q1 | 2026-04-16 | ||
| 2025-Q4 | 2026-02-21 | ||
| 2025-Q3 | 2025-12-23 | ||
| 2025-Q2 | 2025-07-15 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-02-03 | ||
| 2024-Q3 | 2024-11-04 | ||
| 2024-Q2 | 2024-08-26 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-15 | ||
| 2022-Q4 | 2023-01-14 | ||
| 2022-Q3 | 2022-10-16 | ||
| 2022-Q2 | 2022-07-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Shanti Krishna Kanhaiya Construction and Developers Pvt.Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP02252022195037-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP02252022195037&ld=pan&pj=RERAP02252022195037-1&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP02252022195037-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-08-22
- Quarterly Progress Image · 2025-07-15
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-16
- Q3 (Oct - Dec) / 2025-2026 · 2026-02-21
- Q2 (Jul - Sep) / 2025-2026 · 2025-12-23
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-15
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-02-03
- Q2-Jun to Sep / 2024-2025 · 2024-11-04
- Q1-Apr to Jun / 2024-2025 · 2024-08-26
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-15
- Q3-Oct to Dec / 2022-2023 · 2023-01-14
- Q2-Jul to Sep / 2022-2023 · 2022-10-16
- Q1-Apr to Jun / 2022-2023 · 2022-07-15
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Notice of Commencement
- 2026-Q1 · 2026-04-16
- 2025-Q4 · 2026-02-21
- 2025-Q3 · 2025-12-23
- 2025-Q2 · 2025-07-15
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-02-03
- 2024-Q3 · 2024-11-04
- 2024-Q2 · 2024-08-26
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-15
- 2022-Q4 · 2023-01-14
- 2022-Q3 · 2022-10-16
- 2022-Q2 · 2022-07-15