Overview
SKY CITY
Ropar Properties & Builders Pvt Ltd · Rupnagar (Ropar)
Units205
Completion2029-09-30Proposed
Valid to2029-09-30
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 45 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 56 documents · 22 source links |
Registration
Registration
| Promoter | Ropar Properties & Builders Pvt Ltd | |
|---|---|---|
| District | Rupnagar (Ropar) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-RPR70-PR1149 | |
| Valid to | 2029-09-30 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2029-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| Electric Substation NOC | 2025-02-10 |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2024-10-10 |
| Other Document (Drainage NOC) | 2024-09-23 |
| Other Document (Forest NOC) | 2024-09-20 |
| Other Document (PSPCL NOC ) | 2025-01-09 |
| Other Document (Road NOC) | 2025-05-08 |
| Other Document (Sewerage NOC) | 2025-02-03 |
| Other Document (Undertaking regarding NOC) | 2024-11-22 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-02-24 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-01-02 |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹14,55,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 35,005.31 | |
|---|---|---|
| Units | 205 |
Unit types
| PLOT NO. 1 TO 12, 12A AND 14 | 1,463.22 | 14 | RESIDENTIAL PLOTS |
| PLOT NO. 15 TO 20 | 602.01 | 6 | RESIDENTIAL PLOTS |
| PLOT NO. 21 | 107.65 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 22 | 120.77 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 23 TO 24 | 226.45 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 25 TO 44 | 2,508.38 | 20 | RESIDENTIAL PLOTS |
| PLOT NO. 45 TO 46 | 226.45 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 47 TO 48 | 241.55 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 49 TO 50 | 226.45 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 51 TO 60 | 1,254.19 | 10 | RESIDENTIAL PLOTS |
| PLOT NO. 61 TO 70 | 1,241.65 | 10 | RESIDENTIAL PLOTS |
| PLOT NO. 71 TO 72 | 224.19 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 73 | 119.57 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 74 TO 85 | 1,254.19 | 12 | RESIDENTIAL PLOTS |
| PLOT NO. 86 TO 87 | 183.95 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 88 | 99.29 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 89 TO 92 | 418.06 | 4 | RESIDENTIAL PLOTS |
| PLOT NO. 93 TO 95 | 376.26 | 3 | RESIDENTIAL PLOTS |
| PLOT NO. 96 TO 97 | 206.71 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 98 TO 105 | 1,003.35 | 8 | RESIDENTIAL PLOTS |
| PLOT NO. 106 TO 107 | 206.71 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 108 TO 110 | 376.26 | 3 | RESIDENTIAL PLOTS |
| PLOT NO. 111 | 119.01 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 112 TO 117 | 722.56 | 6 | RESIDENTIAL PLOTS |
| PLOT NO. 118 TO 124 | 845.42 | 7 | RESIDENTIAL PLOTS |
| PLOT NO. 125 | 112.27 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 135 | 108.9 | 1 | RESIDENTIAL PLOTS |
| PLOT NO. 152 TO 162 | 1,379.61 | 11 | RESIDENTIAL PLOTS |
| PLOT NO. 163 TO 164 | 222.97 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 165 TO 166 | 248.51 | 2 | RESIDENTIAL PLOTS |
| PLOT NO. 1 TO 15 | 526.76 | 15 | COMMERCIAL PLOTS |
| PLOT NO. 16 TO 19 | 133.78 | 4 | COMMERCIAL PLOTS |
| PLOT NO. 20 TO 33 | 515.05 | 14 | COMMERCIAL PLOTS |
| PLOT NO. 34 TO 35 | 70.23 | 2 | COMMERCIAL PLOTS |
| PLOT NO. 36 TO 39 | 133.78 | 4 | COMMERCIAL PLOTS |
| PLOT NO. 127 | 81.52 | 1 | EWS PLOTS |
| PLOT NO. 126 | 82.36 | 1 | EWS PLOTS |
| PLOT NO. 128 | 80.69 | 1 | EWS PLOTS |
| PLOT NO. 129 | 79.85 | 1 | EWS PLOTS |
| PLOT NO. 130 | 79.01 | 1 | EWS PLOTS |
| PLOT NO. 131 | 78.18 | 1 | EWS PLOTS |
| PLOT NO. 132 | 77.34 | 1 | EWS PLOTS |
| PLOT NO. 133 | 76.51 | 1 | EWS PLOTS |
| PLOT NO. 134 | 75.67 | 1 | EWS PLOTS |
| PLOT NO. 136 TO 151 | 1,337.8 | 16 | EWS PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-10-01 | |
|---|---|---|
| Proposed completion | 2029-09-30 |
Quarterly progress
| 2025-Q2 | 2025-07-14 |
| 2025-Q3 | 2026-01-20 |
| 2025-Q4 | 2026-01-27 |
| 2026-Q1 | 2026-04-25 |
| 2026-Q2 | 2026-07-09 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Ropar Properties & Builders Pvt Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 7 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12188&inPromoter_ID=1274&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-02-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-10-10
- Other Document (Clarification regarding AAI ) · 2025-03-03 · Sign in to download
- Other Document (Clarification regarding EC) · 2025-03-03 · Sign in to download
- Other Document (Drainage NOC) · 2024-09-23
- Other Document (Forest NOC) · 2024-09-20
- Other Document (PSPCL Application form along with payment receipt ) · 2025-01-09 · Sign in to download
- Other Document (PSPCL NOC ) · 2025-01-09
- Other Document (Road NOC) · 2025-05-08
- Other Document (Sewerage NOC) · 2025-02-03
- Other Document (SOLID WASTE) · 2024-12-19 · Sign in to download
- Other Document (Undertaking regarding NOC) · 2024-11-22
- Pollution Clearance from Punjab Pollution Control Board · 2025-02-24
- Pollution Clearance from Punjab Pollution Control Board · 2025-01-02
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2025-02-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-10-10
- Other Document (Drainage NOC) · 2024-09-23
- Other Document (Forest NOC) · 2024-09-20
- Other Document (PSPCL NOC ) · 2025-01-09
- Other Document (Road NOC) · 2025-05-08
- Other Document (Sewerage NOC) · 2025-02-03
- Other Document (Undertaking regarding NOC) · 2024-11-22
- Pollution Clearance from Punjab Pollution Control Board · 2025-02-24
- Pollution Clearance from Punjab Pollution Control Board · 2025-01-02
- Consent details of actual owner of Land
- 2025-Q2 · 2025-07-14
- 2025-Q3 · 2026-01-20
- 2025-Q4 · 2026-01-27
- 2026-Q1 · 2026-04-25
- 2026-Q2 · 2026-07-09
- 2026-Q3 · 2026-10-15