Overview
SKY GREEN CITY
SHRI SAI BUILDCON · BILASPUR
Units85
Booked56 of 85As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2026-10-30Revised · Proposed 2025-06-30
Registered on2021-08-06
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 2 cost heads · 18 quarters |
| Technical report | |
| Site & area | 3 site details · 85 unit types |
| Construction & progress | 4 progress details · 18 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 105 documents · 5 source links |
Registration
Registration
| Promoter | SHRI SAI BUILDCON | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA060821001242 | |
| Registered on | 2021-08-06 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2025-06-30 | |
| Revised completion | 2026-10-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,52,10,000 | |
|---|---|---|
| Construction | ₹1,21,20,000 |
Quarterly money flows
| 2021-Q3 | ₹9,11,400 |
| 2021-Q4 | ₹1,44,046 |
| 2022-Q1 | ₹12,62,940.7 |
| 2022-Q2 | ₹34,53,590.7 |
| 2022-Q3 | ₹70,000.7 |
| 2022-Q4 | ₹560.7 |
| 2023-Q1 | ₹361 |
| 2023-Q2 | ₹3,18,861 |
| 2023-Q3 | ₹7,70,721 |
| 2023-Q4 | ₹32,37,521 |
| 2024-Q1 | ₹9,92,121 |
| 2024-Q2 | ₹24,621 |
| 2024-Q3 | ₹24,621 |
| 2024-Q4 | ₹24,621 |
| 2025-Q1 | ₹4,621 |
| 2025-Q2 | ₹4,621 |
| 2025-Q3 | ₹4,621 |
| 2025-Q4 | ₹4,621 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 85 | |
|---|---|---|
| Booked | 56 | |
| Booked as of | 2025-12-31 |
Unit types
| PLOT-2 | 1 | 1 |
| PLOT-3 | 1 | 1 |
| PLOT-20 | 1 | 1 |
| PLOT-21 | 1 | 0 |
| PLOT-22 | 1 | 1 |
| PLOT-23 | 1 | 1 |
| PLOT-27 | 1 | 0 |
| PLOT-28 | 1 | 0 |
| PLOT-29 | 1 | 0 |
| PLOT-30 | 1 | 0 |
| PLOT-31 | 1 | 0 |
| PLOT-32 | 1 | 0 |
| PLOT-33 | 1 | 0 |
| PLOT-34 | 1 | 0 |
| PLOT-35 | 1 | 0 |
| PLOT-36 | 1 | 0 |
| PLOT-37 | 1 | 0 |
| PLOT-38 | 1 | 0 |
| PLOT-39 | 1 | 0 |
| PLOT-41 | 1 | 0 |
| PLOT-42 | 1 | 0 |
| PLOT-43 | 1 | 0 |
| PLOT-44 | 1 | 0 |
| PLOT-45 | 1 | 0 |
| PLOT-46 | 1 | 0 |
| PLOT-47 | 1 | 0 |
| PLOT-49 | 1 | 0 |
| PLOT-50 | 1 | 0 |
| PLOT-51 | 1 | 0 |
| PLOT-52 | 1 | 1 |
| PLOT-55 | 1 | 1 |
| PLOT-56 | 1 | 1 |
| PLOT-57 | 1 | 1 |
| PLOT-58 | 1 | 1 |
| PLOT-60 | 1 | 1 |
| PLOT-61 | 1 | 1 |
| PLOT-62 | 1 | 1 |
| PLOT-63 | 1 | 1 |
| PLOT-64 | 1 | 0 |
| PLOT-66 | 1 | 0 |
| PLOT-67 | 1 | 1 |
| PLOT-68 | 1 | 1 |
| PLOT-74 | 1 | 1 |
| PLOT-75 | 1 | 1 |
| PLOT-76 | 1 | 1 |
| PLOT-77 | 1 | 1 |
| PLOT-80 | 1 | 1 |
| PLOT-81 | 1 | 1 |
| PLOT-82 | 1 | 1 |
| PLOT-1 | 1 | 1 |
| PLOT-4 | 1 | 1 |
| PLOT-5 | 1 | 1 |
| PLOT-6 | 1 | 1 |
| PLOT-7 | 1 | 1 |
| PLOT-8 | 1 | 1 |
| PLOT-9 | 1 | 1 |
| PLOT-9A | 1 | 1 |
| PLOT-10 | 1 | 1 |
| PLOT-11 | 1 | 1 |
| PLOT-12 | 1 | 1 |
| PLOT-13 | 1 | 1 |
| PLOT-14 | 1 | 1 |
| PLOT-15 | 1 | 1 |
| PLOT-16 | 1 | 1 |
| PLOT-17 | 1 | 1 |
| PLOT-18 | 1 | 1 |
| PLOT-19 | 1 | 1 |
| PLOT-24 | 1 | 1 |
| PLOT-25 | 1 | 0 |
| PLOT-26 | 1 | 1 |
| PLOT-40 | 1 | 1 |
| PLOT-48 | 1 | 1 |
| PLOT-53 | 1 | 1 |
| PLOT-54 | 1 | 1 |
| PLOT-59 | 1 | 1 |
| PLOT-65 | 1 | 1 |
| PLOT-69 | 1 | 1 |
| PLOT-70 | 1 | 1 |
| PLOT-71 | 1 | 1 |
| PLOT-72 | 1 | 0 |
| PLOT-73 | 1 | 1 |
| PLOT-78 | 1 | 1 |
| PLOT-79 | 1 | 1 |
| PLOT-83 | 1 | 1 |
| PLOT-84 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-12-31 | |
| Proposed completion | 2025-06-30 | |
| Revised completion | 2026-10-30 |
Quarterly progress
| 2021-Q3 | 6% |
| 2021-Q4 | 20% |
| 2022-Q1 | 20% |
| 2022-Q2 | 70% |
| 2022-Q3 | 74% |
| 2022-Q4 | 74% |
| 2023-Q1 | 74% |
| 2023-Q2 | 74% |
| 2023-Q3 | 77% |
| 2023-Q4 | 77% |
| 2024-Q1 | 87% |
| 2024-Q2 | 88% |
| 2024-Q3 | 88% |
| 2024-Q4 | 89% |
| 2025-Q1 | 90% |
| 2025-Q2 | 90% |
| 2025-Q3 | 95% |
| 2025-Q4 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHRI SAI BUILDCON | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTU0MA==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities