DOSLAssam Workspace

Overview

SKY LINK HEIGHTS

M/S SUNDARAM DEVELOPERS · JORHAT
Units48
Completion2026-10-31Proposed
Registered on2022-12-21
Valid to2026-12-29
Approvals4

Sections

Property title & search report
Approvals4 approvals
Contract & costs3 cost heads · 10 quarters
Technical report
Site & area2 site details · 8 unit types
Construction & progress2 progress details · 10 quarters
Developer & finance
Developer2 developer details
The evidence
Sources81 documents · 6 source links

Registration

Registration

PromoterM/S SUNDARAM DEVELOPERS
DistrictJORHAT
RegulatorRERA Assam
Registration numberRERAA JO 76 OF 2023-2024
Registered on2022-12-21
Valid to2026-12-29
Status (as filed)Ongoing Projects
Proposed completion2026-10-31