Booked451 of 542As of 2024-03-31
Construction progress100%As of 2024-03-31
Completion2024-09-14Revised · Proposed 2024-06-14
Registered on2020-06-12
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 16 quarters
Technical report
Site & area3 site details · 542 unit types
Construction & progress4 progress details · 16 quarters
Developer & finance
Developer4 developer details
The evidence
Sources112 documents · 6 source links

Registration

Registration

PromoterMAHAVIR INFRACON PVT. LTD. DIRECTOR VINOD BOHRA
DistrictRAJNANDGAON
RegulatorCG RERA
Registration numberPCGRERA120620001118
Registered on2020-06-12
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2024-06-14