Overview
SOBHA ARANYA PHASE-1
SOBHA LIMITED · Gurugram
Units524
Completion2030-12-31Proposed
Registered on2024-04-01
Valid to2030-10-31
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 12 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 43 documents · 3 source links |
Registration
Registration
| Promoter | SOBHA LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/808/540/2024/35 DATED 01.04.2024 | |
| Registered on | 2024-04-01 | |
| Valid to | 2030-10-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2030-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | Licence No 180 of 2023 dated 05.09.2023 | Town & Country Planning Department | |
| Layout Plan | 2024-03-07 | ||
| Building Plan | 2024-03-07 | ||
| I. LICENSE | 2023-09-05 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹18,17,69,18,000 | |
|---|---|---|
| Construction | ₹11,82,70,62,000 | |
| Total | ₹39,75,91,39,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 59,964.167 | |
|---|---|---|
| FAR | 1.25 | |
| Units | 524 |
Unit types
| Apartment/Shops/Other Buildings | 235.94 | 78 |
| Apartment/Shops/Other Buildings | 229.8 | 82 |
| Apartment/Shops/Other Buildings | 222.19 | 6 |
| Apartment/Shops/Other Buildings | 205.81 | 40 |
| Apartment/Shops/Other Buildings | 204.99 | 43 |
| Apartment/Shops/Other Buildings | 192.08 | 3 |
| Apartment/Shops/Other Buildings | 197.53 | 84 |
| Apartment/Shops/Other Buildings | 197.64 | 90 |
| Apartment/Shops/Other Buildings | 184.18 | 6 |
| Apartment/Shops/Other Buildings | 164.1 | 88 |
| Apartment/Shops/Other Buildings | 164.1 | 2 |
| Apartment/Shops/Other Buildings | 164.1 | 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-07-01 | |
|---|---|---|
| Proposed completion | 2030-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SOBHA LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | AXIS BANK LIMITED | |
| Other projects in this city pack | 8 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2820
- https://nominatim.openstreetmap.org/search?q=sector+80%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2024-04-01
- DEMARCATION PLAN · 2024-02-21
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2024-02-21 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2024-02-21
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2024-02-21
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2024-02-21
- EC KARMA SEAC MOM · 2024-06-06 · Sign in to download
- LOI 124 OF 2019 · 2024-06-06 · Sign in to download
- AFFIDAVIT_10% EDC · 2024-06-06 · Sign in to download
- AFFIDAVIT_NCZ · 2024-06-06 · Sign in to download
- ARAVALI NOC · 2024-06-06
- GPA - 29.07.2019 · 2024-06-06 · Sign in to download
- AIRPORT AUTHORITY NOC · 2024-06-06
- LC-IV B · 2024-06-06 · Sign in to download
- BANK UNDERTAKING V1 · 2024-06-06 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2024-06-06 · Sign in to download
- ADDENDUM · 2024-06-06 · Sign in to download
- ZONING PLAN · 2024-06-06
- CA CERTIFICATE FOR PROJECT COST · 2024-06-06 · Sign in to download
- CA CERTIFICATE FOR NET WORTH · 2024-06-06 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2024-06-06 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2024-06-06
- ASSURANCE SEWER CONNECTION · 2024-06-06 · Sign in to download
- DEVELOPMENT AGREEMENT · 2024-06-06 · Sign in to download
- AFFIDAVIT_POWER LINE SHIFTING · 2024-06-06 · Sign in to download
- LC-IV AGREEMENT · 2024-06-06 · Sign in to download
- BR III · 2024-06-06 · Sign in to download
- FIRE SCHEME RECEIVING · 2024-06-06 · Sign in to download
- LOI_180 OF 2023 · 2024-06-06 · Sign in to download
- PHASING AND REVISED ZONING LETTER · 2024-06-06 · Sign in to download
- AFFIDAVIT_4 (2) (L) (D) · 2024-06-06 · Sign in to download
- REVISED ZONING AND PHASING DRAWING · 2024-06-06 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2024-06-06 · Sign in to download
- FOREST NOC_NILP · 2024-06-06
- LICENCE-124 OF 2019 DATED 19.09.2019 · 2024-06-06
- LICENCE_180 OF 2023_05.09.23 · 2024-06-06
- CA CERTIFICATE FOR PROMOTER EQUITY · 2024-06-06 · Sign in to download
- POWER ASSURANCE · 2024-06-06 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2024-06-06 · Sign in to download
- ASSURANCE CONSTRUCTION WATER · 2024-06-06 · Sign in to download
- MINING APPROVAL · 2024-06-06
- SITE PLAN APPLIED · 2024-06-06
- Approval for change of bank account · 2025-05-20