Overview
Sobha Bellevue
Sobha Limited · Chandakkadav
Units298
Booked5 of 298
Construction progress0%
Completion2033-12-31Proposed
Registered on2026-08-31
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 6 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 38 documents · 5 source links |
Registration
Registration
| Promoter | Sobha Limited | |
|---|---|---|
| District | Kozhikode | |
| Locality | Chandakkadav | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KKD/135/2026 | |
| Registered on | 2026-08-31 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2033-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/106661/2026 | 2026-08-01 | 2031-07-31 | Feroke Municipality |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 17,477.35 | |
|---|---|---|
| Built-up (m²) | 1,11,656.63 | |
| Towers | 0 | |
| Units | 298 | |
| Booked | 5 |
Unit types
| 3BHK | 70 | 1 | Sobha Bellevue |
| 3BHK | 4 | 0 | Sobha Bellevue |
| 4BHK | 72 | 0 | Sobha Bellevue |
| 4BHK | 2 | 0 | Sobha Bellevue |
| 4BHK | 76 | 3 | Sobha Bellevue |
| 4BHK | 74 | 1 | Sobha Bellevue |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 0% | |
|---|---|---|
| Start | 2026-08-01 | |
| Proposed completion | 2033-12-31 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Sobha Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | DCB Bank Ltd | |
| Other projects in this city pack | 8 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Sobha Limited |
| Engineer | SOBHA LIMITED |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/12179
- https://rera.kerala.gov.in/projects?district=591&page=7
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=k4fwjV2xnODNkO9rVRjeT%2BFOAu28t9RBgNUDGRKlkw74WLjiGwyv6uQjLX%2BBGh%2F1CRhxg%2F7KBKrwrtiy9wHokDSTq7KUe6tajM2IpPZ%2F1zWhm0g6751wJxxFMhgsnCBemDYpG6en7FijPzU1H3c0OSAc4z0QmOoswGFd5GMWJXnhVmfmg%2BG0HA%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=12179&Division=1&UserID=30236&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2026-08-31
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-08-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2026-08-03
- Other · 2026-06-10 · Sign in to download
- Other · 2026-06-10 · Sign in to download
- Other · 2026-06-10 · Sign in to download
- Clearance from Airport Authority of India · 2026-06-08 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2026-06-09 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2026-06-09
- Consent to establish (Clearance from Pollution Control Board) · 2026-06-09 · Sign in to download
- Environment Clearance · 2026-06-08 · Sign in to download
- Initial NOC from Fire and Rescue department · 2026-06-08
- Others · 2026-08-18 · Sign in to download
- Charts and the project schedule · 2026-07-07 · Sign in to download
- List and details of common amenities · 2026-06-23 · Sign in to download
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12
- Plan of firefighting to be executed in the proposed project · 2026-06-12