Overview
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5
Overview
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5
Overview
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5
Overview
Title & ownership
Approvals
Disputes & cases
Contract & costs
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Interest the builder pays on late possession | SBI MCLR + 2% (Karnataka RERA Rules, r.16) |
|---|
| Defect liability | 5 years |
|---|
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
| Escrow bank | Axis Bank · MG Road Bangalore |
|---|
Data room
105 documents filed with K-RERA for this project
₹99 for this report opens Valuation, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 2 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Locked |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 2 | Clear |
| Loan & collateral | – | – | – | – |
Part of the full report. Unlock all 4 sections
| “smilee Celestial”Lapsed · completion date passed | Blue Valley Properties Pvt Ltd | Plot | – | Aug 2019 |
| 1 Lakhmulti Storey Housing DoddanagamangalaLapsed · completion date passed | Rajiv Gandhi Housing Corporation | Apartment | 323 sqft carpet (as filed) | Mar 2024 |
| 1 Lakhmulti Storey Housing GoolimangalaLapsed · completion date passed | Rajiv Gandhi Housing Corporation Pvt Ltd | Apartment | 323–484 sqft carpet (as filed) | Mar 2024 |
| A B AnanthaActive · 84% built | Amaravathi Builders | Apartment | 753–972 sqft carpet (as filed) | Jan 2027 |
| Abhee NandikaCompleted · OC 22-04-2022 | ABHEE DEVELOPERS | Apartment | 786 sqft carpet (as filed) | Completed |
| Abhee Prakruthi Villa PlotsCompleted (regulator flag) | M/s.Abhee Developers | Plot | – | Completed |
| Abhee PrideCompleted · OC 18-04-2026 | ABHEE VENTURES PRIVATE LIMITED | Apartment | 688–842 sqft carpet (as filed) | Completed |
| Abhee Serenity SpringsActive · 35% built | Abhee Ventures | Apartment | 1,000–1,575 sqft | Jun 2030 |
8 of 270 other projects in Electronic City, A to Z. Status is taken from each project's own filing.
All 279 projects in Electronic City → · Sobha's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5 in the interactive atlas
₹99 for this report opens Valuation, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Valid as of this reportValidity ended
| Power NOC | Filed with the registration | |
|---|---|---|
| Fire NOC | Filed with the registration | |
| Environmental clearance | SEIAA 137 CON 2019 · issued 20 Mar 2020 | Clear |
| Airport height NOC | permissible top elevation 1040 m above mean sea level | |
| Pollution board (CFE) | consent order W-350032 · issued 6 Aug 2025 · valid until 30 Jun 2030 | Clear |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2026 |
₹99 for this report opens Valuation, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 13 km, G K LAYOUT |
|---|
| Nearest storm drain | about 3 km to the north-east, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed pond |
| Electricity, built | 0% | |
|---|---|---|
| Indoor Sports facility, built | 0% | |
| Gym, built | 0% | |
| Power Backup, built | 50% |
As the promoter reported it
| Main structure | 100% · planned by 6 Jan 2025 | |
|---|---|---|
| Electrical and plumbing finishing | 100% · planned by 4 Jul 2026 | |
| Completion | 100% | |
| Completion, accountant | 100.7% of the estimated cost spent |
| Schedule end | 4 Jul 2026 | |
|---|---|---|
| RERA completion date | 31 Dec 2026 | |
| Work began, as filed | 1 Apr 2021 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
|---|---|---|
| Fire safety | Filed with the registration | |
| Environmental clearance | SEIAA 137 CON 2019 · issued 20 Mar 2020 | |
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹85.31 Cr 27.1%Development · ₹228.98 Cr 72.9%
| Estimated cost, at registration | ₹314.29 Cr | |
|---|---|---|
| Cost incurred | ₹316.40 Cr (100.7% of the estimate) | |
| Cost left | ₹-2.11 Cr (spent more than the estimate) | |
| Receivable, sold flats | ₹2.18 Cr |
Sold (280) 100%
| Sold, Q3 2025-26 | 280 / 280 · 0 available | |
|---|---|---|
| Sold, Q4 2025-26 | 280 / 280 · 0 available | |
| Sold, Q1 2026-27 | 280 / 280 · 0 available | |
| Sold, Q2 2026-27 | 280 / 280 · 0 available | |
| Unsold, Q2 2026-27 | 0 | |
| Sold in Q4 2025-26 | 0 | |
| Sold in Q1 2026-27 | 0 | |
| Sold in Q2 2026-27 | 0 | |
| 3 BHK, sold | 280 / 280 |
| Escrow bank | Axis Bank · MG Road Bangalore | |
|---|---|---|
| Designated account, collected | ₹1.40 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹3.59 Cr in Q2 2026-27 | |
| Escrow account, Q2 2026-27 | ₹3.59 Cr withdrawn |
| K-RERA registrations under this promoter | 118 | |
|---|---|---|
| Marked completed | 61 | |
| Past promised date, not completed | 7 | |
| Revoked or withdrawn | 7 | |
| Other phases under this promoter name | 114 | |
| With a filed extension or completion | 65 (58 completed, 7 extended) | |
| Average schedule slip | 12 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 28.7 m
Taluk average; not a reading at the site.
| Groundwater | Anekal taluk average, July 2023: 21.3 m below ground | |
|---|---|---|
| What it means | 20-40 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 2 CGWB wells in Anekal taluk read in this class | |
| Through the year | January 2025: 0.5 m (2 wells), Pre-monsoon 2025: 0.6 m (2 wells), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Anekal taluk (the median where there are several) | |
| Water supply, as filed | Local authority |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 3 km to the north-east, tertiary drain | |
|---|---|---|
| Metro, operational | about 7 km, Bommasandra | |
| Metro, under construction | about 17 km, Bellandur |
| Kempegowda Airport | 64 | 45.5 |
| MG Road (CBD) | 30.5 | 26 |
| Manyata Tech Park | 41 | 31.5 |
| ITPL, Whitefield | 30.5 | 22 |
| Ecospace, Bellandur ORR | 24 | 16.5 |
| Electronic City Ph 1 | 13 | 9 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | about 1.5 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 1 km, named Attibele on OpenStreetMap |