Overview
SOBHA RIDGE WHISPERING HILL
SOBHA LIMITED · Pin Code 695017
Units110
Booked110 of 110
Construction progress54%
Completion2030-04-30Proposed
Registered on2024-01-11
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 12 unit types |
| Construction & progress | 3 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 50 documents · 5 source links |
Registration
Registration
| Promoter | SOBHA LIMITED | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | Pin Code 695017 | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/TVM/012/2024 | |
| Registered on | 2024-01-11 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2030-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | UE2/BA/106/23 | 2023-12-20 | 2028-12-19 | Thiruvananthapuram Corporation |
| Development Permit | UE2/BA/106/23 | 2023-12-20 | 2028-12-19 | Thiruvananthapuram Corporation |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,849 | |
|---|---|---|
| Built-up (m²) | 30,551.38 | |
| Towers | 0 | |
| Units | 110 | |
| Booked | 110 |
Unit types
| A2 3 BHK | 13 | 13 | BLOCK 1 |
| A3 3 BHK | 14 | 14 | BLOCK 1 |
| A1 3.5 BHK with DH | 13 | 13 | BLOCK 1 |
| A4 3.5 BHK with DH | 13 | 13 | BLOCK 1 |
| A5 3.5 BHK with DH | 1 | 1 | BLOCK 1 |
| A6 3.5 BHK with DH | 1 | 1 | BLOCK 1 |
| B1 3 BHK | 13 | 13 | BLOCK 2 |
| B4 3 BHK | 14 | 14 | BLOCK 2 |
| B2 4 BHK with DH | 13 | 13 | BLOCK 2 |
| B3 4 BHK with DH | 13 | 13 | BLOCK 2 |
| B5 4 BHK with DH | 1 | 1 | BLOCK 2 |
| B6 4 BHK with DH | 1 | 1 | BLOCK 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 54% | |
|---|---|---|
| Start | 2024-07-31 | |
| Proposed completion | 2030-04-30 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q4 |
| 2023-2024 Q1 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SOBHA LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | AXIS BANK | |
| Other projects in this city pack | 2 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Sobha Limited |
| Engineer | Sobha Limited |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11469
- https://rera.kerala.gov.in/projects?district=601&page=18
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=jV9vgWsey%2BAvUevYBIHM9hPoTxejy6urrGIFNKKLNjNgbpE7qKIwpgJDvzMABXn5GqZp0J68TgbrrKdxeqhCUlj6Cs4HsApTHIkc7LxaVfQqZG5Ips0F%2BI3F92dixx6TjybiqwpRUy9bFfInAr3WfKnTl104xEYRcUGmL2tVIuXYk8Zqi9texw%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11469&Division=1&UserID=32121&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2024-01-11
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-12-27
- Copy of Valid Building Permit · 2023-12-27
- Detailed technical specifications to be adopted in the project · 2024-01-01 · Sign in to download
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2023-12-29 · Sign in to download
- Site Plan / Site Map · 2023-12-27
- Other · 2023-12-19 · Sign in to download
- Other · 2023-12-19 · Sign in to download
- Other · 2023-12-20 · Sign in to download
- Clearance from Airport Authority of India · 2023-12-26 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2023-12-29 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2023-12-29 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2023-12-20
- Consent to establish (Clearance from Pollution Control Board) · 2023-12-20 · Sign in to download
- Environment Clearance · 2023-12-20 · Sign in to download
- Initial NOC from Fire and Rescue department · 2023-12-20
- Permission from Water and sewerage department · 2023-12-29 · Sign in to download
- Charts and the project schedule · 2024-01-01 · Sign in to download
- List and details of common amenities · 2023-12-29 · Sign in to download
- Plan of firefighting to be executed in the proposed project · 2023-12-27
- Plan of firefighting to be executed in the proposed project · 2023-12-27
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of firefighting to be executed in the proposed project · 2024-01-06
- Plan of Use of renewable energy to be executed in the proposed project · 2023-12-27
- Plan of Use of renewable energy to be executed in the proposed project · 2024-01-06