Living with our elder son & Family since more than one years ,peaceful atmosphere,Environment friendly & good for Senior's Citizens to enjoying life after Service retirement.
SS K28 Sep 2026★★★★★
Excellent views from balcony. This complex is coming up in a certain way. It's got a very premium look and prices are also expensive. Sharing some photos from different time frames
Bbishal kumar27 Jul 2025★★★★★
As on date of visit (27July2025), first building is ready, with few families already staying. Amenities are under construction. The road outside are not good
Land · ₹68.21 Cr 36.3%Development · ₹119.60 Cr 63.7%
Form 4
Estimated cost, at registration
₹187.81 Cr
Cost incurred
₹201.54 Cr (107.3% of the estimate)
Cost left
₹-13.73 Cr (spent more than the estimate)
Collected from buyers
₹203.99 Cr
Receivable, sold flats
₹1.33 Cr
Sales
Sold vs unsold, Q1 2026-27
Sold (113) 100%
Sold per quarter
K-RERA inventory
Sold, Q3 2025-26
113 / 113 · 0 available
Sold, Q4 2025-26
113 / 113 · 0 available
Sold, Q1 2026-27
113 / 113 · 0 available
Unsold, Q1 2026-27
0
Sold in Q4 2025-26
0
Sold in Q1 2026-27
0
Compliance
Escrow, Q1 2026-27
Escrow and filings
Escrow bank
RATNAKAR BANK
Designated account, collected
₹1.08 Cr in Q1 2026-27
Designated account, withdrawn
₹1.11 Cr in Q1 2026-27
Escrow account, Q1 2026-27
₹1.11 Cr withdrawn
Track record
Average schedule slip
DOSL builder track
K-RERA registrations under this promoter
118
Marked completed
61
Past promised date, not completed
7
Revoked or withdrawn
7
Other phases under this promoter name
114
With a filed extension or completion
64 (57 completed, 7 extended)
Average schedule slip
12 months
Not verified yet: Cost left vs buyer dues; Land cost revision; Unregistered agreements, over 10% paid.
Site photos, Q1 2026-27
Not verified yet: Value; Max loan; Borrower margin; Developer's project loan; Example unit; Calculation; Records searched to; Building plan; Unregistered agreements, over 10% paid; Sale deed in favour of.
Basemap: Esri, OpenStreetMap contributors
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.