Overview
SOLITAIRE-22
RISECON CONSTRUCTION LLP · Rewari
Units664
Completion2030-10-30Proposed
Valid to2030-10-31
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 8 documents · 2 source links |
Registration
Registration
| Promoter | RISECON CONSTRUCTION LLP | |
|---|---|---|
| District | Rewari | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-RWR-909-2026 | |
| Valid to | 2030-10-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2030-10-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | LICENSE NO. 214 OF 2025 DATED 31.10.2025 (VALID UPTO 30.10.2030) | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | 2026-04-01 | ||
| I. LICENSE NO. 214 OF 2025 | 2025-10-31 | ||
| II. APPROVAL OF BUILDING PLAN | 2026-04-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹35,00,92,000 | |
|---|---|---|
| Construction | ₹1,39,92,00,000 | |
| Total | ₹2,08,54,18,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 18,413.1675 | |
|---|---|---|
| Units | 664 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 59.99 | 332 |
| Apartment/Shops/Other Buildings | 59.98 | 118 |
| Apartment/Shops/Other Buildings | 51.81 | 214 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-04-15 | |
|---|---|---|
| Proposed completion | 2030-10-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RISECON CONSTRUCTION LLP | |
|---|---|---|
| Escrow bank | AXIS BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/view_project/project_preview_open/4037
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2026-03-30
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2026-04-07 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2026-04-07
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2026-04-07
- PAYMENT PLAN · 2026-05-27