Overview
Solitaire Galleria
Trimurti Homes Private Limited · Ludhiana
Units24
Completion2031-03-27Proposed
Valid to2031-03-27
Approvals14
Sections
| Property title & search report | |
|---|---|
| Approvals | 14 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 10 unit types |
| Construction & progress | 2 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 47 documents · 18 source links |
Registration
Registration
| Promoter | Trimurti Homes Private Limited | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PC0435 | |
| Valid to | 2031-03-27 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2031-03-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| CLU Certificate | |
| CLU Certificate | |
| Electric Substation NOC | 2026-04-28 |
| Electric Substation NOC | 2026-05-12 |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| NOC from NHAI/ PWD | 2026-04-16 |
| NOC from NHAI/ PWD | 2026-04-17 |
| Other Document (Affidavit regarding submission of NOCs) | 2026-03-31 |
| Other Document (BDPO NOC) | 2026-02-11 |
| Other Document (Drainage NOC in promoter name) | 2026-04-29 |
| Other Document (Forest NOC) | 2026-04-23 |
| Pollution Clearance from Punjab Pollution Control Board | 2026-05-13 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹13,26,96,045 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,541.208 | |
|---|---|---|
| Units | 24 |
Unit types
| SCO No. 1 | 118.89 | 1 | COMMERCIAL SCOS |
| SCO No. 2 | 119.79 | 1 | COMMERCIAL SCOS |
| SCO No. 3 | 120.68 | 1 | COMMERCIAL SCOS |
| SCO No. 4 | 121.58 | 1 | COMMERCIAL SCOS |
| SCO No. 5 | 122.47 | 1 | COMMERCIAL SCOS |
| SCO No. 6 | 574.17 | 1 | COMMERCIAL SCOS |
| SCO No. 7 and 8 | 100.335 | 2 | COMMERCIAL SCOS |
| SCO No. 9 | 104.28 | 1 | COMMERCIAL SCOS |
| SCO No. 10 to 21 | 117.058 | 12 | COMMERCIAL SCOS |
| SCO No. 22 to 44 | 111.48 | 3 | COMMERCIAL SCOS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-03-27 | |
|---|---|---|
| Proposed completion | 2031-03-27 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Trimurti Homes Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| CA | ANIL KRISHAN AND ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12703&inPromoter_ID=3630&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2026-04-28
- Electric Substation NOC · 2026-05-12
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2026-04-16
- NOC from NHAI/ PWD · 2026-04-17
- Other Document (Access to Colony from the Competent Authority) · 2026-05-13 · Sign in to download
- Other Document (Architect Certificate regd. EC and AAI) · 2026-04-11 · Sign in to download
- Other Document (BDPO NOC) · 2026-02-11
- Other Document (Drainage NOC in promoter name) · 2026-04-29
- Other Document (Forest NOC) · 2026-04-23
- Other Document (letter to CA regd. exemp. of EC and AAI) · 2026-05-13 · Sign in to download
- Other Document (PSTCL HT LT Lines) · 2026-02-11 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2026-05-13
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2026-04-28
- Electric Substation NOC · 2026-05-12
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2026-04-16
- NOC from NHAI/ PWD · 2026-04-17
- Other Document (Affidavit regarding submission of NOCs) · 2026-03-31
- Other Document (BDPO NOC) · 2026-02-11
- Other Document (Drainage NOC in promoter name) · 2026-04-29
- Other Document (Forest NOC) · 2026-04-23
- Pollution Clearance from Punjab Pollution Control Board · 2026-05-13
- 2026-Q3 · 2026-10-15