Overview
South Park Street-1
Garish Chopra · Ludhiana
Units15
Completion2030-09-11Proposed
Valid to2030-09-11
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 46 documents · 17 source links |
Registration
Registration
| Promoter | Garish Chopra | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PC0460 | |
| Valid to | 2030-09-11 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2030-09-11 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| CLU Certificate | |
| CLU Certificate | |
| Electric Substation NOC | 2025-10-07 |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2025-06-14 |
| NOC from NHAI/ PWD | 2026-02-23 |
| Other Document (Affidavit regarding submission of NOCs) | 2026-06-06 |
| Other Document (Drainage NOC) | 2026-02-25 |
| Other Document (Forest NOC in the name of CA) | 2025-08-01 |
| Other Document (Forest NOC in the name of promoter) | 2026-02-26 |
| Other Document (NOC from ADC Rural Dev Office) | 2025-08-01 |
| Pollution Clearance from Punjab Pollution Control Board | 2026-02-06 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹5,66,71,539 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,065.43 | |
|---|---|---|
| Units | 15 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Plot No. 1 to 3 | 119.84 | 3 | COMMERCIAL PLOTS |
| Plot No. 4 to 10 | 107.18 | 7 | COMMERCIAL PLOTS |
| Plot No. 11 to 15 | 142.45 | 5 | COMMERCIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-09-12 | |
|---|---|---|
| Proposed completion | 2030-09-11 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q3 | 2026-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Garish Chopra | |
|---|---|---|
| Type | Individual | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12782&inPromoter_ID=3716&inPromoterType=1
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Borewell Registration certificate from Central Ground Water Authority · 2026-05-29
- CLU Certificate
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-10-07
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2025-06-14
- NOC from NHAI/ PWD · 2026-02-23
- Other Document (Access to Colony from the Competent Authority) · 2026-04-13 · Sign in to download
- Other Document (Architect Certificate regd. EC and AAI) · 2026-06-06 · Sign in to download
- Other Document (Clar. regd. inventory details in CTE from PPCB) · 2026-06-06 · Sign in to download
- Other Document (Drainage NOC) · 2026-02-25
- Other Document (Experience of Architect) · 2026-06-06 · Sign in to download
- Other Document (Forest NOC in the name of CA) · 2025-08-01
- Other Document (Forest NOC in the name of promoter) · 2026-02-26
- Other Document (letter to CA regd. exemp. of EC and AAI) · 2026-02-24 · Sign in to download
- Other Document (NOC from ADC Rural Dev Office) · 2025-08-01
- Other Document (PSTCL HT LT Lines) · 2025-08-04 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2026-02-06
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2025-10-07
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2025-06-14
- NOC from NHAI/ PWD · 2026-02-23
- Other Document (Affidavit regarding submission of NOCs) · 2026-06-06
- Other Document (Drainage NOC) · 2026-02-25
- Other Document (Forest NOC in the name of CA) · 2025-08-01
- Other Document (Forest NOC in the name of promoter) · 2026-02-26
- Other Document (NOC from ADC Rural Dev Office) · 2025-08-01
- Pollution Clearance from Punjab Pollution Control Board · 2026-02-06
- 2026-Q3 · 2026-10-12