Overview
Sowparnika River View Gardens Phase 2
Sowparnika Projects · Pin Code 695019
Units52
Booked52 of 52
Construction progress100%As of 2023-07-07
Completion2024-12-31Revised · Proposed 2024-12-31
Registered on2021-08-27
Approvals1
Cases1
Complaints1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 1 case · 1 project complaint |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 5 progress details · 14 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 5 professional firms |
| The evidence | |
| Sources | 6 documents · 7 source links |
Registration
Registration
| Promoter | Sowparnika Projects | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | Pin Code 695019 | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/146/2021 | |
| Registered on | 2021-08-27 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2024-12-31 | |
| Revised completion | 2024-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | NEI/BA/175/14 | 2014-06-18 | 2017-06-17 | Corporation of Thiruvananthapuram |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Filed on |
|---|---|---|---|---|
| 180/2023 | K-RERA Kerala | Complaint | Pending | 2023-11-06 |
Complaints & cases
| Cases | 1 | |
|---|---|---|
| Project complaints | 1 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,537 | |
|---|---|---|
| Built-up (m²) | 3,982.97 | |
| Towers | 1 | |
| Units | 52 | |
| Booked | 52 |
Unit types
| Type | Units | Booked | Tower |
|---|---|---|---|
| 2BHK | 24 | 24 | Sowparnika RVG Phase 2 |
| 3BHK | 28 | 28 | Sowparnika RVG Phase 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-07-07 | |
| Start | 1900-01-01 | |
| Proposed completion | 2024-12-31 | |
| Revised completion | 2024-12-31 |
Quarterly progress
| Quarter |
|---|
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2023-2024 Q4 |
| 2024-2025 Q4 |
| 2023-2024 Q1 |
| 2023-2024 Q2 |
| 2023-2024 Q3 |
| 2022-2023 Q4 |
| 2021-2022 Q1 |
| 2022-2023 Q3 |
| 2022-2023 Q1 |
| 2022-2023 Q2 |
| 2021-2022 Q3 |
| 2021-2022 Q4 |
Extensions
| Valid to |
|---|
| 2024-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Sowparnika Projects | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Axis Bank Ltd | |
| Other projects in this city pack | 3 |
Professional firms
| Architect | Sowparnika Projects & Infrastructure P Ltd |
| Architect | Sowparnika Projects & Infrastructure P Ltd |
| Engineer | Sowparnika Projects & Infrastructure Pvt Ltd |
| CA | Y S Shetty & Co |
| CA | Y S Shetty & Co |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/complaint-info?complaint_id=2113
- https://rera.kerala.gov.in/complaint-list?ruling_by=all&page=39
- https://rera.kerala.gov.in/projects/10595
- https://rera.kerala.gov.in/projects?district=601&page=18
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=PFAoOSb87i9MB%2FT5eXNY8DQKlQcPrM7nTlujKnoCTcH%2B21EwxcNvg1JUrKcOT6MxOYuN%2BJsg0nzBJA3j0vXysiyL6eS87tZrsCAsJPhaBxIiNA%2BY8U2zXNfbipJavYs%2FqKSsWmX%2FiRrevWRe5pqRadI4BMkCXUFw0EexCovZTFHcZiTP%2B53obQ%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=10595&Division=1&UserID=30641&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Extension Certificate · Sign in to download
- Extension Order · Sign in to download
- Signed project certificate · 2021-08-27
- Extension certificate · 2024-05-27 · Sign in to download