Overview
SPEEDWAY AVENUE
PYRAMID TOWNSHIPS PRIVATE LIMITED · Gautam Buddha Nagar
Units309
Completion2026-11-14Revised · Proposed 2022-08-31
Registered on2017-10-03
Valid to2026-11-14
Approvals6
Complaints18As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 18 project complaints · 19 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 116 unit types |
| Construction & progress | 3 progress details · 25 quarters · 3 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 85 documents · 32 source links |
Registration
Registration
| Promoter | PYRAMID TOWNSHIPS PRIVATE LIMITED | |
|---|---|---|
| District | Gautam Buddha Nagar | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ12103 | |
| Registered on | 2017-10-03 | |
| Valid to | 2026-11-14 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2022-08-31 | |
| Revised completion | 2026-11-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Original permit | BP19/1021 | 2014-08-28 | 2019-02-22 | Yamuna Expressway Authority |
| Revalidated permit | BP | 2017-11-29 | 2022-11-03 | Yamuna Expressway Authority |
| Original permit | BP19/1021 | 2018-08-28 | 2019-02-22 | Yamuna Expressway Authority |
| Revalidated permit | BP19/1021 | 2018-08-28 | 2028-07-10 | Yamuna Expressway Authority |
| Original permit | BP19/1021 | 2018-08-28 | 2019-02-22 | Yamuna Expressway Authority |
| Revalidated permit | BP19/1021 | 2018-08-28 | 2028-07-10 | Yamuna Expressway Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 18 | |
|---|---|---|
| Promoter | 19 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,04,03,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 10,090 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 21 | |
| Units | 309 |
Unit types
| 1 BHK | 47 | 2 | 1A | 1 |
| 2 BHK | 63 | 2 | 1A | 1 |
| 3 BHK | 81 | 2 | 1A | 1 |
| 2 BHK | 64 | 4 | 1A | 2 |
| 3 BHK | 81 | 2 | 1A | 2 |
| 2 BHK | 64 | 4 | 1A | 3 |
| 3 BHK | 81 | 2 | 1A | 3 |
| 2 BHK | 64 | 4 | 1A | 4 |
| 3 BHK | 81 | 2 | 1A | 4 |
| 2 BHK | 64 | 4 | 1A | 5 |
| 3 BHK | 81 | 2 | 1A | 5 |
| 2 BHK | 64 | 4 | 1A | 6 |
| 3 BHK | 81 | 2 | 1A | 6 |
| 2 BHK | 64 | 4 | 1A | 7 |
| 3 BHK | 81 | 2 | 1A | 7 |
| 2 BHK | 64 | 4 | 1A | 8 |
| 3 BHK | 81 | 2 | 1A | 8 |
| 2 BHK | 64 | 4 | 1A | 9 |
| 3 BHK | 81 | 2 | 1A | 9 |
| 2 BHK | 64 | 4 | 1A | 10 |
| 3 BHK | 81 | 2 | 1A | 10 |
| 2 BHK | 64 | 4 | 1A | 11 |
| 3 BHK | 81 | 2 | 1A | 11 |
| 2 BHK | 64 | 4 | 1A | 12 |
| 3 BHK | 81 | 2 | 1A | 12 |
| 2 BHK | 64 | 4 | 1A | 13 |
| 3 BHK | 81 | 2 | 1A | 13 |
| 2 BHK | 64 | 4 | 1A | 14 |
| 3 BHK | 81 | 2 | 1A | 14 |
| 2 BHK | 64 | 4 | 1A | 15 |
| 3 BHK | 81 | 2 | 1A | 15 |
| OTHER | 136 | 6 | 1A | 16 |
| PENTHOUSE | 123 | 6 | 1A | 18 |
| 2 BHK | 67 | 3 | 2A | 1 |
| 2 BHK | 65 | 3 | 2A | 1 |
| 2 BHK | 70 | 6 | 2A | 2 |
| 2 BHK | 70 | 6 | 2A | 3 |
| 2 BHK | 70 | 6 | 2A | 4 |
| 2 BHK | 70 | 6 | 2A | 5 |
| 2 BHK | 70 | 6 | 2A | 6 |
| 2 BHK | 70 | 6 | 2A | 8 |
| 2 BHK | 70 | 6 | 2A | 9 |
| 2 BHK | 70 | 6 | 2A | 7 |
| 2 BHK | 70 | 6 | 2A | 10 |
| 2 BHK | 70 | 6 | 2A | 11 |
| 2 BHK | 70 | 6 | 2A | 12 |
| 2 BHK | 70 | 6 | 2A | 13 |
| 2 BHK | 70 | 6 | 2A | 14 |
| 2 BHK | 70 | 6 | 2A | 15 |
| 2 BHK | 70 | 6 | 2A | 16 |
| 2 BHK | 70 | 6 | 2A | 17 |
| PENTHOUSE | 128 | 6 | 2A | 18 |
| 2 BHK | 56 | 1 | 3A | 1 |
| 3 BHK | 81 | 1 | 3A | 1 |
| 4 BHK | 135 | 1 | 3A | 1 |
| 2 BHK | 72 | 1 | 3A | 2 |
| 3 BHK | 81 | 2 | 3A | 2 |
| 4 BHK | 135 | 2 | 3A | 2 |
| 2 BHK | 72 | 1 | 3A | 3 |
| 3 BHK | 81 | 2 | 3A | 3 |
| 4 BHK | 135 | 2 | 3A | 3 |
| 2 BHK | 72 | 1 | 3A | 4 |
| 3 BHK | 81 | 2 | 3A | 4 |
| 4 BHK | 135 | 2 | 3A | 4 |
| 2 BHK | 72 | 1 | 3A | 5 |
| 3 BHK | 81 | 2 | 3A | 5 |
| 4 BHK | 135 | 2 | 3A | 5 |
| 2 BHK | 72 | 1 | 3A | 6 |
| 3 BHK | 81 | 2 | 3A | 6 |
| 4 BHK | 135 | 2 | 3A | 6 |
| 2 BHK | 72 | 1 | 3A | 7 |
| 3 BHK | 81 | 2 | 3A | 7 |
| 4 BHK | 135 | 2 | 3A | 7 |
| 2 BHK | 72 | 1 | 3A | 8 |
| 3 BHK | 81 | 2 | 3A | 8 |
| 4 BHK | 135 | 2 | 3A | 8 |
| 2 BHK | 72 | 1 | 3A | 9 |
| 3 BHK | 81 | 2 | 3A | 9 |
| 4 BHK | 135 | 2 | 3A | 9 |
| 2 BHK | 72 | 1 | 3A | 10 |
| 3 BHK | 81 | 2 | 3A | 10 |
| 4 BHK | 135 | 2 | 3A | 10 |
| 2 BHK | 72 | 1 | 3A | 11 |
| 3 BHK | 81 | 2 | 3A | 11 |
| 4 BHK | 135 | 2 | 3A | 11 |
| 2 BHK | 72 | 1 | 3A | 12 |
| 3 BHK | 81 | 2 | 3A | 12 |
| 4 BHK | 135 | 2 | 3A | 12 |
| 2 BHK | 72 | 1 | 3A | 13 |
| 3 BHK | 81 | 2 | 3A | 13 |
| 4 BHK | 135 | 2 | 3A | 13 |
| 2 BHK | 72 | 1 | 3A | 14 |
| 3 BHK | 81 | 2 | 3A | 14 |
| 4 BHK | 135 | 2 | 3A | 14 |
| 2 BHK | 72 | 1 | 3A | 15 |
| 3 BHK | 81 | 2 | 3A | 15 |
| 4 BHK | 135 | 2 | 3A | 15 |
| 2 BHK | 72 | 1 | 3A | 16 |
| 3 BHK | 81 | 2 | 3A | 16 |
| 4 BHK | 135 | 2 | 3A | 16 |
| 2 BHK | 72 | 1 | 3A | 17 |
| 3 BHK | 81 | 2 | 3A | 17 |
| 4 BHK | 135 | 2 | 3A | 17 |
| 2 BHK | 72 | 1 | 3A | 18 |
| 3 BHK | 81 | 2 | 3A | 18 |
| 4 BHK | 135 | 2 | 3A | 18 |
| 2 BHK | 72 | 1 | 3A | 19 |
| 3 BHK | 81 | 2 | 3A | 19 |
| 4 BHK | 135 | 2 | 3A | 19 |
| 2 BHK | 72 | 1 | 3A | 20 |
| 2 BHK | 72 | 1 | 3A | 21 |
| PENTHOUSE | 226 | 2 | 3A | 20 |
| PENTHOUSE | 145 | 2 | 3A | 20 |
| PENTHOUSE | 0 | 0 | 1A | 19 |
| PENTHOUSE | 0 | 0 | 2A | 19 |
| OTHER | 0 | 0 | 1A | 17 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2015-05-01 | |
|---|---|---|
| Proposed completion | 2022-08-31 | |
| Revised completion | 2026-11-14 |
Quarterly progress
| 2020-Q2 | |
| 2020-Q3 | |
| 2020-Q4 | |
| 2021-Q1 | |
| 2021-Q2 | |
| 2021-Q3 | |
| 2021-Q4 | |
| 2022-Q1 | |
| 2022-Q2 | |
| 2022-Q3 | |
| 2022-Q4 | |
| 2023-Q1 | |
| 2023-Q2 | |
| 2023-Q3 | |
| 2023-Q4 | |
| 2024-Q1 | 74% |
| 2024-Q2 | 74% |
| 2024-Q3 | 74% |
| 2024-Q4 | 76% |
| 2025-Q1 | 79% |
| 2025-Q2 | 77% |
| 2025-Q3 | 78% |
| 2025-Q4 | 80% |
| 2026-Q1 | 81% |
| 2026-Q2 | 86% |
Extensions
| Valid to | Reason |
|---|---|
| 2026-11-14 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2026-11-14 | |
| 2026-11-14 | Extension of validity on account of Force Majeure as per MoHUA advisory dated |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PYRAMID TOWNSHIPS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | PUNJAB NATIONAL BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=AIh302FSs+0=&hfFlag=9emr4VdBw22M7BGjKtJWMPDI4s5cHQZP&NPJ6RAme=dGFPIfFpSEzOnV/fLK0j8cm/Eccd6CwQ&PaURJEMAN4=ZL9MNERkNdYTckyBMf74PQ==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GAUTAM%20BUDDHA%20NAGAR
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=AIh302FSs%2B0=
- Other Plan(If Any) · 2018-07-29
- Waste Disposal Plan · 2018-07-30
- Water Supply Plan · 2018-07-30
- Electricity Supply Plan · 2018-07-30
- Development Work Plan · 2018-07-30
- CA CERTIFICATE · 2018-07-29 · Sign in to download
- ARCHITECT CERTIFICATE · 2018-07-29 · Sign in to download
- ENGINEERS CERTIFICATE · 2018-07-29 · Sign in to download
- Sanctioned Layout Plan (Of Entire Project) · 2017-08-21
- Commencement Certificate · 2017-08-21
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- 2020-Q2
- 2020-Q3
- 2020-Q4
- 2021-Q1
- 2021-Q2
- 2021-Q3
- 2021-Q4
- 2022-Q1
- 2022-Q2
- 2022-Q3
- 2022-Q4
- 2023-Q1
- 2023-Q2
- 2023-Q3
- 2023-Q4
- 2024-Q1
- 2024-Q2
- 2024-Q3
- 2024-Q4
- 2025-Q1
- 2025-Q2
- 2025-Q3
- 2025-Q4
- 2026-Q1
- 2026-Q2