DOSLKarnataka Workspace

Overview

SRI SAI DEVELOPERS

SREEDEVI · Koppal
Completion2023-12-31Proposed
Registered on2022-12-31
Valid to2023-12-31
Approvals8
Complaints0

Sections

Property title & search report
Approvals8 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads
Technical report
Construction & progress2 progress details
Developer & finance
Developer4 developer details
The evidence
Sources163 documents · 11 source links

Registration

Registration

PromoterSREEDEVI
DistrictKoppal
RegulatorK-RERA
Registration numberPRM/KA/RERA/1266/390/PR/311222/005575
Registered on2022-12-31
Valid to2023-12-31
Project typePlotted Development
Status (as filed)APPROVED
Proposed completion2023-12-31