Overview
SRK VISTAS
SRI RADHA KRISHNA INFRA DEVELOPERS · Guntur
Units30
Completion2031-12-03Proposed
Registered on2026-06-03
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 30 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 24 documents · 9 source links |
Registration
Registration
| Promoter | SRI RADHA KRISHNA INFRA DEVELOPERS | |
|---|---|---|
| District | Guntur | |
| Regulator | AP RERA | |
| Registration number | P07110086706 | |
| Registered on | 2026-06-03 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2031-12-03 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1143/0053/B/TDP/PTRU/2025 | 2025-12-03 | Commissioner,APCRDA |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹13,50,20,000 | |
|---|---|---|
| Construction | ₹14,03,65,000 | |
| Total | ₹27,53,85,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,495.19 | |
|---|---|---|
| Built-up (m²) | 9,949.85 | |
| Units | 30 |
Unit types
| G+2 | 250.86 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 252.96 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 480.66 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 250.86 | 1 |
| G+2 | 252.96 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-12-03 | |
|---|---|---|
| Proposed completion | 2031-12-03 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SRI RADHA KRISHNA INFRA DEVELOPERS | |
|---|---|---|
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFb1Q9dF4sUJ5oTL43SeK6nt119K1/YGhXr7wXeEGZ04J6RKoEl91tH8mp7XsqZE2jWS+F7FB6n73L/OFu/1tXSath0L2uSfOU58c4etjb+xX
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE