Overview
STAR ENCLAVE-III
EMPIRE COLONIZERS PRIVATE LIMITED · Ludhiana
Units135
Completion2022-10-30Proposed
Valid to2024-04-30
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details · 26 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 34 source links |
Registration
Registration
| Promoter | EMPIRE COLONIZERS PRIVATE LIMITED | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH44-PR0486 | |
| Valid to | 2024-04-30 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2022-10-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Application for renewal of any of the NOCs/ Licenses | 2006-10-30 |
| CLU Certificate | |
| License as Promoter from competent Authority | 2006-05-05 |
| License to develop colony or society from Competent Authority |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹5,61,17,377 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 38,084.89 | |
|---|---|---|
| Units | 135 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Residential Plots | 313.5 | 119 | PLOTS RESIDENTIALS |
| Commercial Plots | 83.61 | 16 | PLOTS COMMERCIALS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2006-12-31 | |
|---|---|---|
| Proposed completion | 2022-10-30 |
Quarterly progress
| 2019-Q3 | 2023-03-29 |
| 2019-Q4 | 2023-03-29 |
| 2020-Q1 | 2023-03-29 |
| 2020-Q2 | 2023-03-29 |
| 2020-Q3 | 2023-03-29 |
| 2020-Q4 | 2023-03-29 |
| 2021-Q1 | 2023-03-29 |
| 2021-Q2 | 2023-03-29 |
| 2021-Q3 | 2023-03-29 |
| 2021-Q4 | 2023-03-29 |
| 2022-Q1 | 2023-03-29 |
| 2022-Q2 | 2023-03-29 |
| 2022-Q3 | 2023-03-29 |
| 2022-Q4 | 2023-03-29 |
| 2023-Q1 | 2025-01-14 |
| 2023-Q2 | 2025-01-14 |
| 2023-Q3 | 2025-01-14 |
| 2023-Q4 | 2025-01-14 |
| 2024-Q1 | 2025-01-14 |
| 2024-Q2 | 2025-01-14 |
| 2024-Q3 | 2025-01-14 |
| 2024-Q4 | 2025-01-14 |
| 2025-Q1 | 2026-04-01 |
| 2025-Q2 | 2026-04-01 |
| 2025-Q3 | 2026-04-01 |
| 2025-Q4 | 2026-04-01 |
Extensions
| Valid to |
|---|
| 2024-04-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | EMPIRE COLONIZERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Indian Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10018&inPromoter_ID=1025&inPromoterType=2
- Approved Layout Plan
- Approved Project Site Map · Sign in to download
- Approved Sanctioned Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Application for renewal of any of the NOCs/ Licenses · 2006-10-30
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License as Promoter from competent Authority · 2006-05-05
- License to develop colony or society from Competent Authority
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- Application for renewal of any of the NOCs/ Licenses · 2006-10-30
- CLU Certificate
- License as Promoter from competent Authority · 2006-05-05
- License to develop colony or society from Competent Authority
- Extension order · Sign in to download
- 2019-Q3 · 2023-03-29
- 2019-Q4 · 2023-03-29
- 2020-Q1 · 2023-03-29
- 2020-Q2 · 2023-03-29
- 2020-Q3 · 2023-03-29
- 2020-Q4 · 2023-03-29
- 2021-Q1 · 2023-03-29
- 2021-Q2 · 2023-03-29
- 2021-Q3 · 2023-03-29
- 2021-Q4 · 2023-03-29
- 2022-Q1 · 2023-03-29
- 2022-Q2 · 2023-03-29
- 2022-Q3 · 2023-03-29
- 2022-Q4 · 2023-03-29
- 2023-Q1 · 2025-01-14
- 2023-Q2 · 2025-01-14
- 2023-Q3 · 2025-01-14
- 2023-Q4 · 2025-01-14
- 2024-Q1 · 2025-01-14
- 2024-Q2 · 2025-01-14
- 2024-Q3 · 2025-01-14
- 2024-Q4 · 2025-01-14
- 2025-Q1 · 2026-04-01
- 2025-Q2 · 2026-04-01
- 2025-Q3 · 2026-04-01
- 2025-Q4 · 2026-04-01