Overview
SUMINTRA RESIDENCY
RAJKUNWAR CONSTRUCTION PRIVATE LIMITED · Patna
Booked3As of 2026-09-30
Construction progress50%As of 2026-09-30
Completion2028-08-27Proposed
Registered on2024-02-28
Valid to2028-08-27
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details |
| Construction & progress | 4 progress details · 11 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 15 source links |
Registration
Registration
| Promoter | RAJKUNWAR CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP12437-001/140/R-1651/2024 | |
| Registered on | 2024-02-28 | |
| Valid to | 2028-08-27 | |
| Project type | Residential | |
| Status (as filed) | RERA Registered Projects | |
| Proposed completion | 2028-08-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance | 2028-08-27 | |
| Fire NOC | 2029-09-29 | DIRECTOR-CUM-STATEFIREOFFICER |
| Airport NOC | 2028-08-27 | AIRPORT AUTHORITY OF INDIA |
| Water Supply Permission | 2028-08-27 | |
| Other approval | 2028-08-27 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹70,00,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,264.94 | |
|---|---|---|
| Built-up (m²) | 2,328.94 | |
| FAR | 2.2 | |
| Towers | 1 | |
| Booked | 3 | |
| Booked as of | 2026-09-30 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 50% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2023-08-28 | |
| Proposed completion | 2028-08-27 |
Quarterly progress
| 2026-Q3 | 2026-10-15 | 50% | 3 |
| 2026-Q2 | 2026-07-21 | ||
| 2026-Q1 | 2026-04-22 | ||
| 2025-Q4 | 2026-01-20 | ||
| 2025-Q3 | 2025-10-25 | ||
| 2025-Q2 | 2025-07-21 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-11 | ||
| 2024-Q3 | 2024-10-09 | ||
| 2024-Q2 | 2024-10-03 | ||
| 2024-Q1 | 2024-10-03 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAJKUNWAR CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | IDBI BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP20230812437_001
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP20230812437&ld=pan&pj=RERAP20230812437_001&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP20230812437_001
- https://rera.bihar.gov.in/RCpage.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Sanctioned Building Plan
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- CA certificate · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Sanction Certificate for Bank Construction Finance · Sign in to download
- Upload Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-15
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-21
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-22
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-20
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-25
- Q1 (Apr - Jun) / 2025-2026 · 2025-07-21
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-11
- Q2-Jul to Sep / 2024-2025 · 2024-10-09
- Q1-Apr to Jun / 2024-2025 · 2024-10-03
- Q4-Jan to Mar / 2023-2024 · 2024-10-03
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2026-Q2 · 2026-07-21
- 2026-Q1 · 2026-04-22
- 2025-Q4 · 2026-01-20
- 2025-Q3 · 2025-10-25
- 2025-Q2 · 2025-07-21
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-11
- 2024-Q3 · 2024-10-09
- 2024-Q2 · 2024-10-03
- 2024-Q1 · 2024-10-03