Overview
Sushma Capital
Towncity Realtors Private Limited · Sahibzada Ajit Singh Nagar (Mohali)
Units145
Completion2024-02-14Proposed
Valid to2024-02-14
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 28 unit types |
| Construction & progress | 2 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 23 source links |
Registration
Registration
| Promoter | Towncity Realtors Private Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PC0091 | |
| Valid to | 2024-02-14 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2024-02-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-02-26 |
| License as Promoter from competent Authority | 2018-07-13 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2018-11-24 | |
| NOC from Mining Department | Permissions (Received) | 2019-02-08 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,20,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 20,903.184 | |
|---|---|---|
| Towers | 9 | |
| Maximum floors | 24 | |
| Units | 145 |
Unit types
| SCF Type 1 | 354.69 | 2 | BLOCK NO 1 |
| SCF Type 2 | 183.97 | 2 | BLOCK NO 1 |
| SCF - Type 3 | 184.72 | 7 | BLOCK NO 1 |
| SCF Type 4 | 249.66 | 1 | BLOCK NO 1 |
| SCF Type 5 | 164.34 | 1 | BLOCK NO 1 |
| SCF Type 6 | 262.76 | 11 | BLOCK NO 1 |
| SCF Type 1 | 107.29 | 7 | BLOCK NO 2 |
| SCF - Type 2 | 105.94 | 4 | BLOCK NO 2 |
| SCF - Type 3 | 103.05 | 1 | BLOCK NO 2 |
| SCF Type 1 | 179 | 1 | BLOCK NO 3 |
| SCF - Type 2 | 183.97 | 2 | BLOCK NO 3 |
| SCF - Type 3 | 184.72 | 9 | BLOCK NO 3 |
| SCF Type 1 | 103.77 | 1 | BLOCK NO 4 |
| SCF - Type 2 | 105.22 | 4 | BLOCK NO 4 |
| SCF - Type 3 | 107.29 | 9 | BLOCK NO 4 |
| SCF Type 1 | 103.77 | 1 | BLOCK NO 5 |
| SCF - Type 2 | 105.22 | 4 | BLOCK NO 5 |
| SCF - Type 3 | 107.29 | 9 | BLOCK NO 5 |
| SCF Type 1 | 103.77 | 1 | BLOCK NO 6 |
| SCF - Type 2 | 105.22 | 4 | BLOCK NO 6 |
| SCF - Type 3 | 107.29 | 9 | BLOCK NO 6 |
| SCF Type 1 | 103.77 | 1 | BLOCK NO 7 |
| SCF - Type 2 | 105.22 | 4 | BLOCK NO 7 |
| SCF - Type 3 | 107.29 | 9 | BLOCK NO 7 |
| SCF - Type 1 | 160.6 | 2 | BLOCK NO 8 |
| SCF Type 2 | 182.02 | 15 | BLOCK NO 8 |
| SCF Type 1 | 182.95 | 2 | BLOCK NO 9 |
| SCF - Type 2 | 184.72 | 22 | BLOCK NO 9 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-02-15 | |
|---|---|---|
| Proposed completion | 2024-02-14 |
Quarterly progress
| 2020-Q4 | 2021-02-01 |
| 2021-Q1 | 2021-04-12 |
| 2021-Q2 | 2021-07-13 |
| 2021-Q3 | 2021-10-12 |
| 2021-Q4 | 2022-01-14 |
| 2022-Q1 | 2022-04-14 |
| 2022-Q2 | 2022-07-15 |
| 2022-Q3 | 2022-11-18 |
| 2022-Q4 | 2023-01-19 |
| 2023-Q1 | 2023-04-25 |
| 2023-Q2 | 2023-09-18 |
| 2023-Q3 | 2024-01-17 |
| 2023-Q4 | 2024-04-10 |
| 2024-Q1 | 2024-04-15 |
| 2024-Q2 | 2024-07-30 |
| 2024-Q3 | 2025-02-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Towncity Realtors Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10784&inPromoter_ID=1645&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2018-02-26
- License as Promoter from competent Authority · 2018-07-13
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-11-24
- NOC from Mining Department · 2019-02-08
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Environment Clearance certificate/ NOC · 2018-02-26
- License as Promoter from competent Authority · 2018-07-13
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-11-24
- NOC from Mining Department · 2019-02-08
- 2020-Q4 · 2021-02-01
- 2021-Q1 · 2021-04-12
- 2021-Q2 · 2021-07-13
- 2021-Q3 · 2021-10-12
- 2021-Q4 · 2022-01-14
- 2022-Q1 · 2022-04-14
- 2022-Q2 · 2022-07-15
- 2022-Q3 · 2022-11-18
- 2022-Q4 · 2023-01-19
- 2023-Q1 · 2023-04-25
- 2023-Q2 · 2023-09-18
- 2023-Q3 · 2024-01-17
- 2023-Q4 · 2024-04-10
- 2024-Q1 · 2024-04-15
- 2024-Q2 · 2024-07-30
- 2024-Q3 · 2025-02-14