Overview
Sushma Enclave
Transform Developers · Patna
Units12
Completion2023-11-15Proposed
Registered on2019-11-11
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 3 unit types |
| Construction & progress | 2 progress details · 17 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 28 documents · 23 source links |
Registration
Registration
| Promoter | Transform Developers | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP83108-1/1003/R-754/2019 | |
| Registered on | 2019-11-11 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2023-11-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹39,12,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 769.53 | |
|---|---|---|
| Built-up (m²) | 1,018.72 | |
| FAR | 2.17 | |
| Towers | 1 | |
| Units | 12 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 4 | Sushma Enclave |
| 2 BHK | 4 | Sushma Enclave |
| 2 BHK | 4 | Sushma Enclave |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-07-01 | |
|---|---|---|
| Proposed completion | 2023-11-15 |
Quarterly progress
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-11 |
| 2022-Q4 | 2023-03-26 |
| 2022-Q3 | 2023-03-26 |
| 2022-Q2 | 2022-07-20 |
| 2022-Q1 | 2022-07-19 |
| 2021-Q4 | 2022-03-26 |
| 2021-Q3 | 2021-12-06 |
| 2021-Q2 | 2021-08-30 |
| 2021-Q1 | 2021-04-23 |
| 2020-Q4 | 2021-01-23 |
| 2020-Q3 | 2020-11-26 |
| 2020-Q2 | 2020-07-27 |
| 2020-Q1 | 2020-07-27 |
| 2019-Q4 | 2020-01-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Transform Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Bank of Baroda | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP05302019183108-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP05302019183108-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-11
- Q3-Oct to Dec / 2022-2023 · 2023-03-26
- Q2-Jul to Sep / 2022-2023 · 2023-03-26
- Q1-Apr to Jun / 2022-2023 · 2022-07-20
- Q4-Jan to Mar / 2021-2022 · 2022-07-19
- Q3-Oct to Dec / 2021-2022 · 2022-03-26
- Q2-Jul to Sep / 2021-2022 · 2021-12-06
- Q1-Apr to Jun / 2021-2022 · 2021-08-30
- Q4-Jan to Mar / 2020-2021 · 2021-04-23
- Q3-Oct to Dec / 2020-2021 · 2021-01-23
- Q2-Jul to Sep / 2020-2021 · 2020-11-26
- Q1-Apr to Jun / 2020-2021 · 2020-07-27
- Q4-Jan to Mar / 2019-2020 · 2020-07-27
- Q3-Oct to Dec / 2019-2020 · 2020-01-31
- Project Photogragh · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-11
- 2022-Q4 · 2023-03-26
- 2022-Q3 · 2023-03-26
- 2022-Q2 · 2022-07-20
- 2022-Q1 · 2022-07-19
- 2021-Q4 · 2022-03-26
- 2021-Q3 · 2021-12-06
- 2021-Q2 · 2021-08-30
- 2021-Q1 · 2021-04-23
- 2020-Q4 · 2021-01-23
- 2020-Q3 · 2020-11-26
- 2020-Q2 · 2020-07-27
- 2020-Q1 · 2020-07-27
- 2019-Q4 · 2020-01-31