Overview
Sushma Infinium
Sushma Buildtech Limited · Sahibzada Ajit Singh Nagar (Mohali)
Units989
Completion2022-09-13Proposed
Valid to2022-09-13
Approvals7
Cases4
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Disputes & cases | 4 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 21 unit types |
| Construction & progress | 2 progress details · 11 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 20 documents · 20 source links |
Registration
Registration
| Promoter | Sushma Buildtech Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PC0014 | |
| Valid to | 2022-09-13 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2022-09-13 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Permissions (Applied) | 2018-05-10 |
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Clearances (Received) | 2015-11-20 |
| License as Promoter from competent Authority | 2017-08-10 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2015-11-02 |
| Pollution Clearance from Punjab Pollution Control Board | 2017-09-11 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| CC/780/2017 | State Consumer Disputes Redressal Commission Chandigarh |
| CC/621/2017 | State Consumer Disputes Redressal Commission Chandigarh |
| CC/621/2017 | State Consumer Commission Chandigarh |
| CC/780/2017 | State Consumer Commission Chandigarh |
Complaints & cases
| Cases | 4 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹100 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 14,166 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 16 | |
| Units | 989 |
Unit types
| Unit | 11 | 3 | SUSHMA INFINIUM |
| Unit | 12.3 | 2 | SUSHMA INFINIUM |
| Unit | 14.84 | 180 | SUSHMA INFINIUM |
| Unit | 22.9 | 430 | SUSHMA INFINIUM |
| Unit | 22.9 | 15 | SUSHMA INFINIUM |
| Unit | 23.68 | 120 | SUSHMA INFINIUM |
| Unit | 29.06 | 2 | SUSHMA INFINIUM |
| Unit | 23.07 | 4 | SUSHMA INFINIUM |
| Unit | 30.46 | 3 | SUSHMA INFINIUM |
| Unit | 30.73 | 1 | SUSHMA INFINIUM |
| Unit | 31.29 | 4 | SUSHMA INFINIUM |
| Unit | 37.82 | 56 | SUSHMA INFINIUM |
| Unit | 30.73 | 1 | SUSHMA INFINIUM |
| Unit | 37.82 | 2 | SUSHMA INFINIUM |
| Unit | 67.98 | 75 | SUSHMA INFINIUM |
| Unit | 50.81 | 71 | SUSHMA INFINIUM |
| Unit | 50.81 | 4 | SUSHMA INFINIUM |
| Unit | 80.84 | 12 | SUSHMA INFINIUM |
| Unit | 60.92 | 1 | SUSHMA INFINIUM |
| Unit | 91.09 | 2 | SUSHMA INFINIUM |
| Unit | 60.92 | 1 | SUSHMA INFINIUM |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-01-20 | |
|---|---|---|
| Proposed completion | 2022-09-13 |
Quarterly progress
| 2020-Q4 | 2021-02-01 |
| 2021-Q1 | 2021-04-12 |
| 2021-Q2 | 2021-07-13 |
| 2021-Q3 | 2021-10-12 |
| 2021-Q4 | 2022-01-14 |
| 2022-Q1 | 2022-04-14 |
| 2022-Q2 | 2022-07-15 |
| 2022-Q3 | 2022-11-18 |
| 2022-Q4 | 2023-01-19 |
| 2023-Q1 | 2023-04-25 |
| 2023-Q2 | 2023-09-18 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Sushma Buildtech Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10030&inPromoter_ID=1037&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Sanctioned Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-05-10
- Building Permit Issue from Municipal Authority · 2012-01-20 · Sign in to download
- CLU Certificate
- Completion/ Phase Completion certificate from Municipal/ Competent Authority · 2017-12-15 · Sign in to download
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2015-11-20
- License as Promoter from competent Authority · 2017-08-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2015-11-02
- Other Document (Structural Vetting Certificate by IIT Roorkee) · 2016-01-01 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2017-09-11
- Project Land Khasra Report or Plan
- Building/ Tower/ Block Construction · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2018-05-10
- CLU Certificate
- Environment Clearance certificate/ NOC · 2015-11-20
- License as Promoter from competent Authority · 2017-08-10
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2015-11-02
- Pollution Clearance from Punjab Pollution Control Board · 2017-09-11
- 2020-Q4 · 2021-02-01
- 2021-Q1 · 2021-04-12
- 2021-Q2 · 2021-07-13
- 2021-Q3 · 2021-10-12
- 2021-Q4 · 2022-01-14
- 2022-Q1 · 2022-04-14
- 2022-Q2 · 2022-07-15
- 2022-Q3 · 2022-11-18
- 2022-Q4 · 2023-01-19
- 2023-Q1 · 2023-04-25
- 2023-Q2 · 2023-09-18