Overview
SV SAHASRA
SV DEVELOPERS · Kandlakoya
Units66
Booked0 of 66
Completion2024-06-14Revised · Proposed 2024-06-14
Registered on2020-07-06
Valid to2024-06-14
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 66 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 7 documents · 3 source links |
Registration
Registration
| Promoter | SV DEVELOPERS | |
|---|---|---|
| District | Medchal-Malkajgiri | |
| Locality | Kandlakoya | |
| Regulator | Telangana RERA | |
| Registration number | P02200001947 | |
| Registered on | 2020-07-06 | |
| Valid to | 2024-06-14 | |
| Project type | Residential | |
| Status (as filed) | On-Going Project | |
| Proposed completion | 2024-06-14 | |
| Revised completion | 2024-06-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date | Authority |
|---|---|---|
| Plan approval | 2018-06-14 | HMDA |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,592.84 | |
|---|---|---|
| Built-up (m²) | 16,841.87 | |
| Towers | 1 | |
| Units | 66 | |
| Booked | 0 |
Unit types
| 2 BHK G01 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G02 | 1 | 0 | SV SAHASRA | 1 |
| 3 BHK G03 | 1 | 0 | SV SAHASRA | 1 |
| 3 BHK G04 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G05 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G06 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G07 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G08 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G09 | 1 | 0 | SV SAHASRA | 1 |
| 3 BHK G10 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK G11 | 1 | 0 | SV SAHASRA | 1 |
| 2 BHK 102 | 1 | 0 | SV SAHASRA | 2 |
| 3 BHK 103 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 105 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 106 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 107 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 109 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 108 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 111 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 101 | 1 | 0 | SV SAHASRA | 2 |
| 3 BHK 104 | 1 | 0 | SV SAHASRA | 2 |
| 3 BHK 110 | 1 | 0 | SV SAHASRA | 2 |
| 2 BHK 202 | 1 | 0 | SV SAHASRA | 3 |
| 3 BHK 203 | 1 | 0 | SV SAHASRA | 3 |
| 3 BHK 204 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 205 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 206 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 207 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 211 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 209 | 1 | 0 | SV SAHASRA | 3 |
| 3 BHK 210 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 201 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 208 | 1 | 0 | SV SAHASRA | 3 |
| 2 BHK 301 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 302 | 1 | 0 | SV SAHASRA | 4 |
| 3 BHK 303 | 1 | 0 | SV SAHASRA | 4 |
| 3 BHK 304 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 305 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 306 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 307 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 308 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 309 | 1 | 0 | SV SAHASRA | 4 |
| 3 BHK 310 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 311 | 1 | 0 | SV SAHASRA | 4 |
| 2 BHK 401 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 402 | 1 | 0 | SV SAHASRA | 5 |
| 3 BHK 403 | 1 | 0 | SV SAHASRA | 5 |
| 3 BHK 404 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 405 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 406 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 407 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 408 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 409 | 1 | 0 | SV SAHASRA | 5 |
| 3 BHK 410 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 411 | 1 | 0 | SV SAHASRA | 5 |
| 2 BHK 501 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 502 | 1 | 0 | SV SAHASRA | 6 |
| 3 BHK 503 | 1 | 0 | SV SAHASRA | 6 |
| 3 BHK 504 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 505 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 506 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 507 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 508 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 509 | 1 | 0 | SV SAHASRA | 6 |
| 3 BHK 510 | 1 | 0 | SV SAHASRA | 6 |
| 2 BHK 511 | 1 | 0 | SV SAHASRA | 6 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2024-06-14 | |
|---|---|---|
| Revised completion | 2024-06-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SV DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rerait.telangana.gov.in/PrintPreview/PrintPreview?q=4fA02UnvszU3%2BpEI2yCN8GSvcvd21PW56wBUpE7GjRqDxWa5OhDTn30%2BFdzU1SCd5%2FeQsopitUCfI%2Fj6PxQRqpqmP16SDydqpE4yLQPPjRAP8N%2FFt%2FSBNBkl9DJRuoLivinALVAWAVg7o%2BfbYef0dinlnPoqAJIG%2Fwyb%2FBiCmpGEtQmSA12B7g%3D%3D
- https://rerait.telangana.gov.in/SearchList/GetShowCertificateFileContent?QueryStringID=UHJvamVjdElEPTI4MjQmRGl2aXNpb249MSZVc2VySUQ9MzgxNjgmUm9sZUlEPTEmQXBwSUQ9MTQwMDAmQWN0aW9uPVNFQVJDSCZDaGFyYWN0ZXJEPTc2JkV4dEFwcElEPQ%3D%3D
- https://rerait.telangana.gov.in/SearchList/Search
- Details of encumbrances · Sign in to download
- Copy of Approval Layout Plan
- Declaration in FORM B · Sign in to download
- Commencement Certificate/Copy of Building Permit/Proceedings
- Copy of Sanctioned Building Plan
- Status of Formation of Legal Entity (Society/Co Op etc.) · Sign in to download
- View Certificate · 2020-07-06