DOSLKarnataka Workspace

Overview

Svamitva Terravana Phase 2

Svamitva Landmarks · Ramanagara
Units63
Booked59 of 63
Construction progress97%
Completion2026-12-31Proposed
Registered on2022-06-16
Valid to2026-12-31
Approvals10
Complaints0

Sections

Property title & search report
Approvals10 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads · 4 quarters
Technical report
Site & area7 site details · 1 unit type
Construction & progress3 progress details · 4 quarters
Developer & finance
Developer4 developer details
The evidence
Sources256 documents · 13 source links

Registration

Registration

PromoterSvamitva Landmarks
DistrictRamanagara
RegulatorK-RERA
Registration numberPRM/KA/RERA/1270/305/PR/160622/004995
Registered on2022-06-16
Valid to2026-12-31
Project typeResidential/Group Housing
Status (as filed)APPROVED
Proposed completion2026-12-31