DOSLChhattisgarh Workspace

Overview

SWARNABHOOMI, PHASE-IV

FORTUNE RESOURCES PRIVATE LIMITED · RAIPUR
Units311
Booked159 of 311As of 2026-06-30
Construction progress92%As of 2026-06-30
Completion2027-07-31Revised · Proposed 2027-03-31
Registered on2024-02-02
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area3 site details · 311 unit types
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer3 developer details
The evidence
Sources78 documents · 7 source links

Registration

Registration

PromoterFORTUNE RESOURCES PRIVATE LIMITED
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA020224001723
Registered on2024-02-02
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2027-03-31
Revised completion2027-07-31