SWARNIMA ERA PHASE- VIII

BDA GROUP · BILASPUR
Units41
Booked13 of 41As of 2026-06-30
Construction progress45%As of 2026-06-30
Completion2030-08-07Revised · Proposed 2030-04-07
Registered on2025-05-09
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 5 quarters
Technical report
Site & area3 site details · 41 unit types
Construction & progress4 progress details · 5 quarters
Developer & finance
Developer3 developer details
The evidence
Sources41 documents · 6 source links

Registration

Registration

PromoterBDA GROUP
DistrictBILASPUR
RegulatorCG RERA
Registration numberPCGRERA090525001924
Registered on2025-05-09
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2030-04-07
Revised completion2030-08-07