Overview
SWASTIK GREENS
PROMINENT ENTERPRISES PRIVATE LIMITED · Gurugram
Units914
Completion2028-03-26Proposed
Registered on2023-12-04
Valid to2028-03-26
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 76 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 2 source links |
Registration
Registration
| Promoter | PROMINENT ENTERPRISES PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/765/497/2023/109 DATED 04.12.2023 | |
| Registered on | 2023-12-04 | |
| Valid to | 2028-03-26 | |
| Status (as filed) | Registered | |
| Proposed completion | 2028-03-26 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 65 OF 2023(27-03-2023) | Town & Country Planning Department | |
| Layout Plan | 2023-06-28 | ||
| Building Plan | |||
| I. LICENCE | 2023-03-27 | ||
| II. LAYOUT PLAN | 2023-06-28 | ||
| III. DEMARCATION PLAN | 2023-08-21 | ||
| IV. ZONING PLAN | 2023-08-21 | ||
| V. NOC ARAVALLI | 2023-09-08 | ||
| VI. NOC FOREST | 2023-03-20 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹9,36,98,74,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹13,19,62,67,000.000002 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1 | |
|---|---|---|
| Units | 914 |
Unit types
| Plot | 4 | |
| Plot | 1 | |
| Plot | 3 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 12 | |
| Plot | 1 | |
| Plot | 4 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 9 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 8 | |
| Plot | 1 | |
| Plot | 6 | |
| Plot | 1 | |
| Plot | 3 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 10 | |
| Plot | 1 | |
| Plot | 16 | |
| Plot | 2 | |
| Plot | 7 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 5 | |
| Plot | 18 | |
| Plot | 2 | |
| Plot | 26 | |
| Plot | 2 | |
| Plot | 26 | |
| Plot | 2 | |
| Plot | 16 | |
| Plot | 14 | |
| Plot | 1 | |
| Plot | 32 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 44 | |
| Plot | 2 | |
| Plot | 59 | |
| Plot | 20 | |
| Plot | 1 | |
| Plot | 40 | |
| Plot | 138 | |
| Plot | 40 | |
| Plot | 6 | |
| Plot | 2 | |
| Plot | 20 | |
| Plot | 2 | |
| Plot | 6 | |
| Plot | 2 | |
| Plot | 9 | |
| Plot | 13 | |
| Plot | 1 | |
| Plot | 4 | |
| Plot | 52 | |
| Plot | 4 | |
| Plot | 12 | |
| Plot | 36 | |
| Plot | 4 | |
| Plot | 2 | |
| Plot | 28 | |
| Plot | 18 | |
| Plot | 2 | |
| Plot | 14 | |
| Plot | 9 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 69 | |
| Plot | 2 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-10-01 | |
|---|---|---|
| Proposed completion | 2028-03-26 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PROMINENT ENTERPRISES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2611
- Registration Certificate · 2023-12-04
- ZONING PLAN · 2023-09-19
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2023-09-19
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2023-09-19
- DEMARCATION PLAN · 2023-09-19
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2023-09-19
- SIZRA · 2023-11-30 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2023-11-20 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2023-11-20
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2023-11-20 · Sign in to download
- CASH FLOW · 2023-11-30 · Sign in to download
- SERVICE PLAN ESTIMATE PART-2 · 2023-11-30
- SERVICE PLAN ESTIMATE PART-1 · 2023-11-30
- SUPERIMPOSED DEMARCATION · 2023-11-30 · Sign in to download
- SERVICE PLAN ESTIMATE PART-3 · 2023-11-30