Overview
TGB NEELGAGAN TOWER-G
TGB REALTY PVT.LTD. · Ghaziabad
Units78
Completion2023-06-30Revised · Proposed 2022-12-31
Registered on2017-10-12
Valid to2023-06-30
Approvals1
Complaints5As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 5 project complaints · 25 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 51 unit types |
| Construction & progress | 3 progress details · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 7 source links |
Registration
Registration
| Promoter | TGB REALTY PVT.LTD. | |
|---|---|---|
| District | Ghaziabad | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ13544 | |
| Registered on | 2017-10-12 | |
| Valid to | 2023-06-30 | |
| Project type | Residential | |
| Status (as filed) | Abeyance | |
| Proposed completion | 2022-12-31 | |
| Revised completion | 2023-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 618 | 2015-03-27 | 2020-03-26 | Ghaziabad Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 5 | |
|---|---|---|
| Promoter | 25 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹16,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 346 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 26 | |
| Units | 78 |
Unit types
| 3 BHK | 96.414 | 1 | TOWER G | GF |
| 3 BHK | 96.414 | 1 | TOWER G | 1 |
| 3 BHK | 96.414 | 1 | TOWER G | 2 |
| 3 BHK | 96.414 | 1 | TOWER G | 3 |
| 3 BHK | 96.414 | 1 | TOWER G | 4 |
| 3 BHK | 96.414 | 1 | TOWER G | 5 |
| 3 BHK | 96.414 | 1 | TOWER G | 6 |
| 3 BHK | 96.414 | 1 | TOWER G | 7 |
| 3 BHK | 96.414 | 1 | TOWER G | 8 |
| 3 BHK | 96.414 | 1 | TOWER G | 9 |
| 3 BHK | 96.414 | 1 | TOWER G | 10 |
| 3 BHK | 96.414 | 1 | TOWER G | 11 |
| 3 BHK | 96.414 | 1 | TOWER G | 12 |
| 3 BHK | 96.414 | 1 | TOWER G | 13 |
| 3 BHK | 96.414 | 1 | TOWER G | 14 |
| 3 BHK | 96.414 | 1 | TOWER G | 15 |
| 3 BHK | 96.414 | 1 | TOWER G | 16 |
| 3 BHK | 96.414 | 1 | TOWER G | 17 |
| 3 BHK | 96.414 | 1 | TOWER G | 18 |
| 3 BHK | 96.414 | 1 | TOWER G | 19 |
| 3 BHK | 96.414 | 1 | TOWER G | 20 |
| 3 BHK | 96.414 | 1 | TOWER G | 21 |
| 3 BHK | 96.414 | 1 | TOWER G | 22 |
| 3 BHK | 96.414 | 1 | TOWER G | 23 |
| 2 BHK | 74.312 | 2 | TOWER G | GF |
| 2 BHK | 74.312 | 2 | TOWER G | 1 |
| 2 BHK | 74.312 | 2 | TOWER G | 2 |
| 2 BHK | 74.312 | 2 | TOWER G | 3 |
| 2 BHK | 74.312 | 2 | TOWER G | 4 |
| 2 BHK | 74.312 | 2 | TOWER G | 5 |
| 2 BHK | 74.312 | 2 | TOWER G | 6 |
| 2 BHK | 74.312 | 2 | TOWER G | 7 |
| 2 BHK | 74.312 | 2 | TOWER G | 8 |
| 2 BHK | 74.312 | 2 | TOWER G | 9 |
| 2 BHK | 74.312 | 2 | TOWER G | 10 |
| 2 BHK | 74.312 | 2 | TOWER G | 11 |
| 2 BHK | 74.312 | 2 | TOWER G | 12 |
| 2 BHK | 74.312 | 2 | TOWER G | 13 |
| 2 BHK | 74.312 | 2 | TOWER G | 14 |
| 2 BHK | 74.312 | 2 | TOWER G | 15 |
| 2 BHK | 74.312 | 2 | TOWER G | 16 |
| 2 BHK | 74.312 | 2 | TOWER G | 17 |
| 2 BHK | 74.312 | 2 | TOWER G | 18 |
| 2 BHK | 74.312 | 2 | TOWER G | 19 |
| 2 BHK | 74.312 | 2 | TOWER G | 20 |
| 2 BHK | 74.312 | 2 | TOWER G | 21 |
| 2 BHK | 74.312 | 2 | TOWER G | 22 |
| 2 BHK | 74.312 | 2 | TOWER G | 23 |
| 2 BHK | 74.312 | 2 | TOWER G | 24 |
| 2 BHK | 74.312 | 2 | TOWER G | 25 |
| 2 BHK | 74.312 | 2 | TOWER G | 26 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2014-03-27 | |
|---|---|---|
| Proposed completion | 2022-12-31 | |
| Revised completion | 2023-06-30 |
Extensions
| Valid to | Reason |
|---|---|
| 2023-06-30 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | TGB REALTY PVT.LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | AXIS BANK LTD. | |
| Other projects in this city pack | 2 |
Professional firms
| Role | Firm |
|---|---|
| Architect | DEEPAK MEHTA ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=StuDCOTyRNc=&hfFlag=q5Tk0QUeJB8oatkp/Oqbxw==&NPJ6RAme=i71AtmwLKY8QZui+TVmWvAmNgyBz4Kup&PaURJEMAN4=ZL9MNERkNdZaiJdBlHmPsA==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadAbeyanceprojectWithParameter
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GHAZIABAD
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=StuDCOTyRNc=