Overview
THE CALISTO
ShreeSiddhi VinayakHomes · Gayatri Nagar B, Maharani Farm, Durgapura
Units42
Booked40 of 42As of 2024-06-30
Completion2024-08-31Revised · Proposed 2022-02-25
Registered on2022-03-11
Valid to2024-08-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 7 site details · 7 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 25 documents · 7 source links |
Registration
Registration
| Promoter | ShreeSiddhi VinayakHomes | |
|---|---|---|
| District | Jaipur | |
| Locality | Gayatri Nagar B, Maharani Farm, Durgapura | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2022/1889 | |
| Registered on | 2022-03-11 | |
| Valid to | 2024-08-31 | |
| Project type | Group Housing | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2022-02-25 | |
| Revised completion | 2024-08-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,95,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹15,95,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,259.95 | |
|---|---|---|
| Built-up (m²) | 5,352 | |
| Towers | 42 | |
| Maximum floors | 6 | |
| Units | 42 | |
| Booked | 40 | |
| Booked as of | 2024-06-30 |
Unit types
| Type 2BHK (107, 207, 307, 407, 507, 607) | 60.12 | 6 | 6 | The Calisto |
| Type 2BHK(104, 204, 304, 404, 504, 604) | 70.34 | 6 | 5 | The Calisto |
| Type 3BHK(101, 201, 301, 401, 501, 601) | 80.07 | 6 | 5 | The Calisto |
| Type 3BHK(102, 202, 302, 402, 502, 602) | 100.58 | 6 | 6 | The Calisto |
| Type 3BHK(103, 203, 303, 403, 503, 603) | 94.84 | 6 | 6 | The Calisto |
| Type 3BHK(105, 205, 305, 405, 505, 605) | 95.33 | 6 | 6 | The Calisto |
| Type 3BHK(106, 206, 306, 406, 506, 606) | 81.33 | 6 | 6 | The Calisto |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-02-28 | |
|---|---|---|
| Proposed completion | 2022-02-25 | |
| Revised completion | 2024-08-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q2 | 2025-08-12 | 40 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ShreeSiddhi VinayakHomes | |
|---|---|---|
| Type | Individual | |
| Escrow bank | AU SMALL FINANCE BANK | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | Prime Tech Design Consultants |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=jaipur%2C+Jaipur%2C+Rajasthan%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.rajasthan.gov.in/ProjectDetail?id=06jbVqhlbZGHW3tgjww5GQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/06jbVqhlbZGHW3tgjww5GQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=06jbVqhlbZGHW3tgjww5GQ%3D%3D&QuarterIdEnc=RXQtwfTEmtE0gcDePQWEOA%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=G86WpMt2qc4%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Other than Plotted)
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Others
- R1_UploadDoc · 2024-06-30 · Sign in to download
- R2_UploadDoc · 2025-07-22 · Sign in to download
- R3_UploadedPath · 2025-07-17 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download