Overview
THE CITYSCAPE
FRENCH BUILDMART PRIVATE LIMITED · Gurugram
Completion2022-09-30Revised
Registered on2022-01-24
Valid to2022-09-30
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 2 unit types |
| Construction & progress | 1 progress detail |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 38 documents · 2 source links |
Registration
Registration
| Promoter | FRENCH BUILDMART PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/527/259/2022/02 DATED 24.01.2022 | |
| Registered on | 2022-01-24 | |
| Valid to | 2022-09-30 | |
| Status (as filed) | Lapsed Project | |
| Revised completion | 2022-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 43 of 2010 dated 08-06-2010 | Town & Country Planning Department | |
| Layout Plan | 2020-05-11 | ||
| Building Plan | 2020-05-11 | ||
| I. LICECNE | 2010-06-08 | ||
| II. BUILDING PLAN | 2020-05-11 | ||
| III. ZONING | 2019-02-06 | ||
| IV. ENVIRONMENT CLEARANCE | 2020-09-03 | ||
| V. HEIGHT NOC | 2018-05-25 | ||
| VI. FOREST | 2010-07-03 | ||
| VII. ZONING | 2019-02-06 | ||
| VIII. SERVICE ESTIMATES | 2020-02-06 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2022-09-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹17,29,27,000 | |
|---|---|---|
| Construction | ₹60,64,94,000 | |
| Total | ₹1,25,67,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 3.5 |
|---|
Unit types
| Type |
|---|
| 1 |
| 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Revised completion | 2022-09-30 |
|---|
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | FRENCH BUILDMART PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1448
- Registration Certificate · 2022-01-24
- HEIGHT NOC · 2020-09-11
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-09-16 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-09-11
- BOARD_RESOLUTION · 2020-09-11 · Sign in to download
- DEMARCATION PLAN · 2020-09-11
- FOREST NOC · 2020-09-11
- NEC · 2020-09-11 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2020-09-15 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-09-11
- LC-IV · 2020-09-11 · Sign in to download
- ENVIRONMENT CLEARANCE · 2020-09-11
- ZONING PLAN · 2020-09-11
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-09-15 · Sign in to download
- LOI · 2020-09-15 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-06-16
- ROAD PLAN · 2021-06-16
- FIRE PLAN · 2021-06-16
- LICENCE RENEWAL DATED 22.10.2018 · 2021-06-16
- STORM WATER PLAN · 2021-06-16
- WATER SUPPLY PLAN · 2021-06-16
- SEWERAGE PLAN · 2021-06-16
- SERVICE ESTIMATE APPROVAL LETTER · 2021-06-16
- SERVICE ESTIMATE REPORT · 2021-06-16 · Sign in to download
- REVISED BR - III DATED 11.05.2020 (TOD) · 2021-06-16 · Sign in to download
- BASEMENT AND TERRACE PLAN · 2021-06-16
- FLOOR PLAN · 2021-06-16
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-06-16
- ELEVATION PLAN · 2021-06-16
- SECTION PLAN · 2021-06-16
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2021-06-16
- FIRE APPROVAL · 2021-06-16
- RENEWAL OF LICENSE DATED 26.04.2021 · 2021-06-16
- ELECTRICITY SUPPLY PLAN · 2022-01-08
- LANDSCAPE PLAN · 2022-01-08
- SOLID WASTE MANAGEMENT PLAN · 2022-01-08
- STREET LIGHT PLAN · 2022-01-08
- SUPER IMPOSED LAYOUT ON DEMACATION PLAN · 2022-01-08