Overview
The Clermont
One City Infrastructure Private Limited · Sahibzada Ajit Singh Nagar (Mohali)
Completion2032-12-31Proposed
Valid to2032-12-31
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 3 site details |
| Construction & progress | 2 progress details · 5 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 70 documents · 17 source links |
Registration
Registration
| Promoter | One City Infrastructure Private Limited | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR1246 | |
| Valid to | 2032-12-31 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2032-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Electric Substation NOC | 2025-07-17 |
| Electric Substation NOC | 2024-12-20 |
| Electric Substation NOC | 2023-02-27 |
| Environment Clearance certificate/ NOC | 2024-11-04 |
| Other Document (Affi. cum clar. regd. area of this project inNOCs) | 2025-07-30 |
| Other Document (Affidavit regarding submission of NOCs) | 2025-07-26 |
| Other Document (Drainage NOC) | 2023-11-30 |
| Other Document (Forest NOC) | 2022-06-22 |
| Pollution Clearance from Punjab Pollution Control Board | 2025-03-04 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,30,10,97,493 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 11,001.37 | |
|---|---|---|
| Towers | 4 | |
| Maximum floors | 5 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-07-23 | |
|---|---|---|
| Proposed completion | 2032-12-31 |
Quarterly progress
| 2025-Q3 | 2025-10-16 |
| 2025-Q4 | 2026-01-12 |
| 2026-Q1 | 2026-04-15 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | One City Infrastructure Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12430&inPromoter_ID=3337&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Commencement Certificate (Mega Project Category) · Sign in to download
- Electric Substation NOC · 2025-07-17
- Electric Substation NOC · 2024-12-20
- Electric Substation NOC · 2023-02-27
- Environment Clearance certificate/ NOC · 2024-11-04
- Other Document (Affi. cum clar. regd. area of this project inNOCs) · 2025-07-30
- Other Document (Architect Certificate regd. AAI and NHAI) · 2025-07-26 · Sign in to download
- Other Document (Drainage NOC) · 2023-11-30
- Other Document (Forest NOC) · 2022-06-22
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-04
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Electric Substation NOC · 2025-07-17
- Electric Substation NOC · 2024-12-20
- Electric Substation NOC · 2023-02-27
- Environment Clearance certificate/ NOC · 2024-11-04
- Other Document (Affi. cum clar. regd. area of this project inNOCs) · 2025-07-30
- Other Document (Affidavit regarding submission of NOCs) · 2025-07-26
- Other Document (Drainage NOC) · 2023-11-30
- Other Document (Forest NOC) · 2022-06-22
- Pollution Clearance from Punjab Pollution Control Board · 2025-03-04
- 2025-Q3 · 2025-10-16
- 2025-Q4 · 2026-01-12
- 2026-Q1 · 2026-04-15
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-15