DOSLDelhi NCR Workspace

Overview

THE CORRIDORS (PHASE 3)

IREO GRACE REALTECH PRIVATE LIMITED · Gurugram
Completion2023-12-31Revised
Registered on2017-12-22
Valid to2023-12-31
Approvals12

Sections

Property title & search report
Approvals12 approvals
Disputes & cases2 registration details
Contract & costs3 cost heads
Technical report
Site & area2 site details · 10 unit types
Construction & progress2 progress details
Developer & finance
Developer4 developer details
The evidence
Sources20 documents · 3 source links

Registration

Registration

PromoterIREO GRACE REALTECH PRIVATE LIMITED
DistrictGurugram
RegulatorHRERA Gurugram
Registration number379 OF 2017 DATED 22.12.2017
Registered on2017-12-22
Valid to2023-12-31
Status (as filed)Lapsed Project
Revised completion2023-12-31