THE MANNAT PARK

MAK INFRA · BASTAR
Units82
Booked56 of 82As of 2026-06-30
Construction progress61%As of 2026-06-30
Completion2029-08-01Revised · Proposed 2029-04-01
Registered on2024-06-11
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 9 quarters
Technical report
Site & area3 site details · 82 unit types
Construction & progress4 progress details · 9 quarters
Developer & finance
Developer3 developer details
The evidence
Sources63 documents · 6 source links

Registration

Registration

PromoterMAK INFRA
DistrictBASTAR
RegulatorCG RERA
Registration numberPCGRERA110624001781
Registered on2024-06-11
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2029-04-01
Revised completion2029-08-01