Overview
THE ORNATE
Overview
THE ORNATE
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | 1 | – | – | Red flag |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | ||
Title & ownership
We haven't verified this for this project yet.
Sign in first, then it is one click.
Approvals
| Layout approval | 1 filed · latest filed 15 Jan 2024 |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Apr 2030 |
Disputes & cases
Builder: EMPRESA ESTATE PRIVATE LIMITED
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| Other status 1 | ||||||
| – | 948 | The Honble CJSD Pune | BANER | – | Filed case | –, Medium: The record does not say whether it is decided. |
This is the only registration under this promoter's exact name in Maharashtra.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified this for this project yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 82 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| – |
| – |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map centred on the pincode area the filing names, approximate: pincode level. The filing names only the pincode area. The marker is its centre and the ring is 20 km; it does not mark the site.
Centre of the filed pincode area; basemap © OpenStreetMap contributors
All projects in Pune → (12 of 4,379 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| Registration number | P52100046463 | |
|---|---|---|
| Registered | 4 Aug 2022 |
Map centred on the pincode area the filing names, approximate: pincode level. The filing names only the pincode area. The marker is its centre and the ring is 20 km; it does not mark the site.
Centre of the filed pincode area; basemap © OpenStreetMap contributors
| RERA completion date | 30 Apr 2030 | |
|---|---|---|
| Registered | 4 Aug 2022 | |
| Completion date first filed | 31 Dec 2029 |
| Architect's certificate, Form 1 | 2 filed · latest filed 27 Mar 2025 | |
|---|---|---|
| Engineer's certificate, Form 2 | 20 filed · latest filed 18 Oct 2026 |
Land · ₹72.92 Cr 22.7%Development · ₹248.19 Cr 77.3%
| Estimated cost, at registration | ₹321.11 Cr |
|---|